Paldiski LNG Terminal
General Information
Promoter
Balti Gaas plc
Operator
Balti Gaas plc
Host Country
Estonia
Status
Planned
Website
Project's URLPublication Approval Status
Approved
Sponsors
Balti Gaas LLC
100%
LNG-N-079
Project
LNG Terminal
Non-FID
Update Date
23/05/2016
Advanced
Description
LNG import and regasification terminal for regional use on the Pakri peninsula on the Easern coast of the Baltic Sea
Regulatory Decisions and
similar material conditions
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Paldiski LNG
Balti Gaas plc
2020
LNG_Tk_EE
EE
37.6 GWh/d
Comment: Construction plan, first step. Unloading capacity at the terminal is 105 GWh/day -
one ship, which is unloaded in about 12h...