Benefits
Main Driver
Market Demand
Main Driver Explanation
Benefit Description
PCI Details
PCI Benefits
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation
prior to the commissioning of the project, Project concerns investment in reverse flow capacity
General Criteria Fulfilled
Yes
Specific Criteria Fulfilled
Competition, Market Integration, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
TRA-N-394 Gassled - Danish upstream system
Schedule
Start Date
End Date
Pre-Feasibility
Feasibility
09/2015
12/2016
FEED
Market Test
Permitting
Supply Contracts
FID
Construction
Commissioning
2022
2022
NDP and PCI Information
Part of NDP
No (Presently a feasibility study for the
Baltic Pipe is carried out in cooperation
between Gaz-System (Polish TSO) and
Energinet.dk.The study will be finalized by
end of 2016. If the study recommends a
capacity of Baltic Pipe well above 3 bcm/y
, this reinforcement project will be
included in NDP.)
NDP Number
Currently PCI
No
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
Yes
Exemption Granted
Yes
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 125 of 620
Current TYNDP : TYNDP 2017 - Annex A