Expected Gas Sourcing
Algeria, Caspian Region, Libya, LNG ()
Benefits
Main Driver
Market Demand
Main Driver Explanation
During last open seaon on the project, shippers have confirmed their interest for reverse capacitites at the Oltingue / Rodersdorf IP.
Benefit Description
Pipelines and Compressor Stations
Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Morelmaison CS
Enable reverse flow from Oltingue
0
Oltingue interconnection station
Enable reverse flow
0
Total
0
Schedule
Start Date
End Date
Pre-Feasibility
12/2010
Feasibility
10/2014
08/2015
FEED
09/2015
12/2016
Market Test
06/2012
Permitting
Supply Contracts
01/2017
FID
07/2015
Construction
03/2017
12/2017
Commissioning
2018
2018
NDP and PCI Information
Part of NDP
Yes (GRTgaz PDD 2015)
NDP Number
na
Currently PCI
No
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
Not Relevant
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%