9DO GH 6D{QH SURMHFW

General Information

Promoter

GRTgaz

Operator

GRTgaz

Host Country

France

Status

Planned

Website

Project's URL

Publication Approval Status

Approved

Sponsors

GRTgaz

100%

TRA-F-43

Project

Pipeline including CS

FID

Update Date

27/05/2016

Advanced

Description

This reinforcement of the French Network consists in the looping of the Bourgogne pipeline (between Etrez and Voisines). In addition to the projetcs

Arc de Dierrey in the North and Gascogne Midi in the South, this project is needed to merge GRTgaz's North and South market zones. It will

contribute to the priority corridor "North South gas interconnections in Western Europe".

Regulatory Decisions and

similar material conditions

Enabled Projects

Project Code Project Name

TRA-N-047 Reverse capacity from France to Germany at Obergailbach

TRA-F-45

Reverse capacity from CH to FR at Oltingue

TRA-F-391 Gascogne-Midi : adaptation of stations in Cruzy and St Martin

Capacity Increments Variant For Modelling

Point

Operator

Year

From Gas System To Gas System Capacity

Liaison Nord Sud

GRTgaz

2018

FRn

FRs

999.0 GWh/d

Comment: merger of balancing zone

GRTgaz

2018

FRs

FRn

999.0 GWh/d

Comment: merger of balancing zone

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 181 of 620

Current TYNDP : TYNDP 2017 - Annex A