Time Schedule

Grant Obtention Date

16/04/2015

Delay Since Last TYNDP

12 months in commissining date / same delay in FID

PCI Details

PCI Benefits

Project aims at fulfilling the infrastructure standard (N-1) rule at regional level in accordance with Article 6(3) of Regulation EU, Project aims at

supplying directly or indirectly at least two Member States

General Criteria Fulfilled

Yes

Specific Criteria Fulfilled

Competition, Market Integration, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

Market Integration - Regional (SEE + Serbia + FYROM) and beyond (e.g. Hungary and through across the NSI gas corridor) Security of Supply

through inter alia source and route diversification- Greece, Bulgaria, Serbia, FYROM, Hungary, Ukraine, Turkey Enhances competition in the

region by introducing new sources and routes of supply Sustainability - Supports back up to renewables and power to gas

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

Alexandroupolis LNG terminal - M/R Amfitriti

762

28

0

Total

28

0

Schedule

Start Date

End Date

Pre-Feasibility

12/2010

Feasibility

01/2014

06/2014

FEED

05/2016

12/2016

Market Test

03/2017

Permitting

12/2010

01/2015

Supply Contracts

FID

12/2016

Construction

04/2017

06/2018

Commissioning

2018

2018

NDP and PCI Information

Part of NDP

No (The Project is not included in the NDP

because it is an Independent Natural Gas

System and therefore the NTSO is not

obliged to include it in the NDP because it

is not the Project's promoter and/or

operator.)

NDP Number

Currently PCI

Yes (6.9.1 )

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM