Expected Gas Sourcing

Black Sea

Time Schedule

Grant Obtention Date

14/10/2015

Delay Since Last TYNDP

3 year

Delay Explanation

New Power Plants demands delay minimum 3 years and harmonization with RO/HU/AT planned capacity booking.

PCI Details

PCI Benefits

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation

prior to the commissioning of the project, Project concerns investment in reverse flow capacity

General Criteria Fulfilled

Yes

Specific Criteria Fulfilled

Competition, Market Integration, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

9iURVIROG (UFVL *\RU

1,000

210

Total

210

Schedule

Start Date

End Date

Pre-Feasibility

06/2014

Feasibility

09/2016

07/2017

FEED

11/2018

04/2020

Market Test

12/2016

Permitting

05/2017

09/2018

Supply Contracts

04/2017

FID

10/2018

Construction

03/2021

12/2022

Commissioning

2022

2022

NDP and PCI Information

Part of NDP

Yes (Hungarian TYNDP 2015)

NDP Number

12.7.

Currently PCI

Yes (6.24.4.)

CBCA Decision

Yes (2016-10-06)

Market Survey

Open Season(2016-12-31)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

No

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 306 of 620

Current TYNDP : TYNDP 2017 - Annex A