Expected Gas Sourcing

Caspian Region, Russia

Time Schedule

Grant Obtention Date

Delay Since Last TYNDP

1 year

Delay Explanation

Russian/Turkey conflict.

PCI Details

PCI Benefits

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation

prior to the commissioning of the project

General Criteria Fulfilled

Yes

Specific Criteria Fulfilled

Competition, Market Integration, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

Hungarian section

+30 MW compressor station, in order to put natural gas from

the Hungarian national system (gas storage, other sources) to

Tesla pipeline.

1,200

361

50

Total

361

50

Schedule

Start Date

End Date

Pre-Feasibility

12/2015

Feasibility

01/2017

12/2017

FEED

10/2016

03/2018

Market Test

10/2016

Permitting

10/2016

03/2018

Supply Contracts

08/2018

FID

03/2018

Construction

09/2018

05/2020

Commissioning

2020

2020

NDP and PCI Information

Part of NDP

Yes (Hungarian TYNDP 2015)

NDP Number

12.15.1. - 12.15.2.

Currently PCI

Yes (6.25.2.)

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

No

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 332 of 620

Current TYNDP : TYNDP 2017 - Annex A