Shannon LNG Terminal and Connecting Pipeline
General Information
Promoter
Shannon LNG
Operator
Shannon LNG
Host Country
Ireland
Status
Planned
Website
Project's URLPublication Approval Status
Approved
Sponsors
LNG-N-030
Project
LNG Terminal
Non-FID
Update Date
19/05/2016
Non-Advanced
Description
Shannon LNG proposes to construct a liquefied natural gas (LNG) terminal on the southern shore of the Shannon Estuary in County Kerry, Ireland.
Shannon LNG has obtained all of the major permits and consents for the LNG project including planning permission for the terminal and 26 KM
export pipeline, pipeline rights of way and foreshore leases and licenses. Shannon LNG has planning permission to bulid a 500 MW CHP plant and
associated 220 kV transmission infrastructure to connect the CHP plant to the national grid. The Shannon LNG terminal is designed and permitted to
export to the national gas grid up to 26.8 million normal cubic metres per day of natural gas. It is currently envisaged the project will have initial
deliverability of 16.1 normal million cubic metres per day.
Regulatory Decisions and
similar material conditions
Schedule
Start Date
End Date
Pre-Feasibility
05/2006
Feasibility
05/2006
09/2007
FEED
07/2016
06/2017
Market Test
01/2010
Permitting
10/2007
12/2009
Supply Contracts
06/2018
FID
06/2018
Construction
07/2018
06/2021
Commissioning
NDP and PCI Information
Part of NDP
Yes (Gas Networks Ireland 2015 Network
Development Plan)
NDP Number
PCI 5.3
Currently PCI
Yes (Project Code 5.3 under Commission
Delegated Regulation (EU) No 1391/2013)
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Negotiated
Considered Tariff Regime
Negotiated
Applied for Exemption
Yes
Exemption Granted
Yes
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 345 of 620
Current TYNDP : TYNDP 2017 - Annex A