Main Driver

Others

Main Driver Explanation

Benefit Description

1.Physical reverse flow between Ireland and Northern Ireland is beneficial to the development of an integrated market on the island of ireland, having

significant importance in the development and operation of a single gas market between both jurisdictions. 2. It would widen the market that is available

to Northern Ireland gas market participants. 3. Contributes to the viability of LNG and storage projects.

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

The work would involve compression and tie-in facilities to the

Irish onshore transmission system. To be determined post

feasibility study.

Total

Schedule

Start Date

End Date

Pre-Feasibility

05/2018

Feasibility

06/2018

05/2019

FEED

06/2019

05/2020

Market Test

06/2018

Permitting

06/2020

05/2021

Supply Contracts

FID

Construction

06/2021

12/2022

Commissioning

2022

2022

NDP and PCI Information

Part of NDP

Yes (Gaslink, Network development Plan

2013)

NDP Number

N/A

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 349 of 620

Current TYNDP : TYNDP 2017 - Annex A