Expected Gas Sourcing
LNG for the terminal may come from any LNG producer in the world . We envisage a liquid LNG market with a crescent importance
Benefits
Main Driver
Others
Main Driver Explanation
Benefit Description
Decontamination of part of Trieste Industrial Harbour. Boost in economic activity in the city, province and region.
Delay Explanation
The temporary suspension of the validity of the July 2009 EIA by Italian Environment Ministry Decree (April 18, 2013), has delayed up to date
the Services Conference procedures, the award of Final Authorization and therefore the project construction and commissioning dates The final
resolution recently issued in February 2015 restoring the validity of the EIA will resume the last phase of permitting process (Services
Conference).