H-gas conversion of L-gas export border points

TRA-N-882

Project

Pipeline including CS

Non-FID

Update Date

20/05/2016

Non-Advanced

Description

Due to the of production of the Groningen field, L-gas export from the Netherlands to Germany is reduced. This projects enables the flow of H-gas

via the existing L-gas border station at Oude Statenzijl. This project is linked to project initiatives of Gasunie Deutschland and GTG Nord.

Regulatory Decisions and

similar material conditions

Capacity Increments Variant For Modelling

Point

Operator

Year

From Gas System To Gas System Capacity

Bunde (DE) / Oude Statenzijl (H) (NL) (GTG Nord)

Gasunie Transport Services B.V.

2020

IB-NLg

DEg

48.0 GWh/d

Gasunie Transport Services B.V.

2022

IB-NLg

DEg

12.0 GWh/d

Gasunie Transport Services B.V.

2024

IB-NLg

DEg

12.0 GWh/d

Gasunie Transport Services B.V.

2026

IB-NLg

DEg

24.0 GWh/d

Gasunie Transport Services B.V.

2027

IB-NLg

DEg

24.0 GWh/d

Bunde (DE) / Oude Statenzijl (H) (NL) (GUD)

Gasunie Transport Services B.V.

2020

IB-NLg

DEg

72.4 GWh/d

Gasunie Transport Services B.V.

2030

IB-NLg

DEg

137.5 GWh/d

Virtual Ips (GTS) NL-DE (Gaspool)

Gasunie Transport Services B.V.

2020

NL

IB-NLg

120.4 GWh/d

Gasunie Transport Services B.V.

2022

NL

IB-NLg

12.0 GWh/d

Gasunie Transport Services B.V.

2024

NL

IB-NLg

12.0 GWh/d

Gasunie Transport Services B.V.

2026

NL

IB-NLg

24.0 GWh/d

Gasunie Transport Services B.V.

2027

NL

IB-NLg

24.0 GWh/d

Gasunie Transport Services B.V.

2030

NL

IB-NLg

137.5 GWh/d