Immingham Storage Co Ltd – Immingham East Terminal

IME-SIS1 - Safety Instrument System Safety Requirement Specification

P & I Design Ltd

DOCUMENT NO: SI277010_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: G DATE: 31.10.14

Tel: + 44 (0)1642 617444

PAGE 2 OF 13

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

Contents

1 REVISION HISTORY.................................................................................................................3 2.0 INTRODUCTION ......................................................................................................................3 2.1 Overview of System.....................................................................................................................3 2.2 Operation......................................................................................................................................4 2.2.1 No. 4 East Tanks ..........................................................................................................................4 2.2.2 General ........................................................................................................................................5 2.2.3 Environmental Considerations ....................................................................................................6 2.3 System Structure .......................................................................................................................7 2.3.1 System Model – No. 4 East Tanks ...............................................................................................7 2.4 Definitions and Abbreviations ..................................................................................................8 3.0 General Requirements ...............................................................................................................9 4.0 Functional Requirements ........................................................................................................10 4.1 No. 4 East Tanks ........................................................................................................................10 4.1.1 SIS Inputs ...................................................................................................................................10 4.1.2 SIS Logic Solvers.......................................................................................................................10 4.1.3 SIS Outputs ................................................................................................................................10 4.2 Interface between the SIS and BPCS .....................................................................................11 5.0 SIF Requirements ....................................................................................................................12