Table of Contents Table of Contents
Previous Page  12 / 189 Next Page
Information
Show Menu
Previous Page 12 / 189 Next Page
Page Background

Immingham Storage Co Ltd – Immingham East Terminal

IME-SIS1 - Safety Instrument System Safety Requirement Specification

P & I Design Ltd

DOCUMENT NO: SI277010_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: G DATE: 31.10.14

Tel: + 44 (0)1642 617444

PAGE 4 OF 13

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

4 East Tanks

The SIS logic solver will be configured for all in scope gasoline tanks, future tanks will be

located in the ROSOV logic panel. Cabling infrastructure will be installed for all tanks to

allow the installation of a tank side valve and relocation to the SIS logic solver should the

tank be required for gasoline duty. The SIS logic solver to be allocated with space and

infrastructure for 7 additional gasoline storage tanks. Each tank on SIS duty will have an

individual tank-side import / export valve that will close on the activation of the independent

high high level switch on that tank or on activation of an individual tank isolation pushbutton

located at the exit of the bund.

All valves will also close on activation of the 4 East Crash Stop.

2.2

Operation

The Safety Instrument Functions are to prevent overfill of the storage tanks.

The No. 4 East tanks will have actuated import/export valves which again will automatically

close on the activation of the independent high high level switch for that particular tank. The

following valves are included in the design:

XV56101 - Tank 561 Import/Export Valve

XV56401 - Tank 564 Import/Export Valve

XV56801 - Tank 568 Import/Export Valve

2.2.1 No. 4 East Tanks

There are six possible import routes. Although there are six pipelines, a batch import process

to any particular tank will only use a single pipeline. As there is no process control system

which confirms the route, this design will operate by closing the tank-side import/export

valve on the tank independent high high alarm activation.

For the No.4 East tanks, on detection of a tank independent high high level, fault or power

supply failure, the output will be removed to the actuator on that tank’s import/export valve,

resulting in the ball valve closing. The valve cannot be re-opened until the independent high

high level, fault or power supply failure are returned to a healthy state. Then on operation of a

momentary reset pushbutton (one on the SIS logic solver panel plus facility for remote

operation) the actuated ball valve will open (if selected to open at local pneumatic control

station).

There is no requirement to override this SIF in the event of an activation of the independent

high high level switch as there is a dedicated export route using hoses under management

procedures which will allow for product to be removed from the tank. Management

controlled use of this is described elsewhere.

The valves will be operated, cycled, periodically on a monthly basis. This will provide a form

of regular stroke testing. Taking this into consideration, and the fact that only one valve will

be open to allow import to any one tank, the SIS shall be designed as a 1oo1 system

throughout, providing all clauses of BS EN 61511 are satisfied.