P & I Design Ltd
Process Instrumentation Consultancy & Design
2 Reed Street, Gladstone Industrial Estate,
Thornaby, TS17 7AF, United Kingdom.
Tel. +44 (0) 1642 617444 Fax. +44 (0) 1642 616447
Web Site:
www.pidesign.co.ukIMMINGHAM STORAGE Co LTD
IMMINGHAM EAST TERMINAL
IME-SIS1
SAFETY INSTRUMENT SYSTEM
SAFETY REQUIREMENT SPECIFICATION
Rev
Date
By
Checked
Approved
Description
Client Ref.
A
27.07.10
D.S. Regan
MM
DRR
Original Issue
B
03.12.10
D.S. Regan
PJP
DRR
Revised as per discussions with
client
Document No.
SI277010_RPT
C
20.12.10
D.S. Regan
PJP
Client
Post FSA Stage 1
D
22.02.11
D.S. Regan
MM
Client
Revised following SIS Design
E
29.06.12
D.S. Regan
MM
Client
Revised following FSA Stage 3
F
19.06.13
D.B.Faulkner
DSR
Client
XV56701 Installed
G
31.10.14
D.B.Faulkner
DSR
ISCo
Scope Reduced to Tanks 561, 564
& 568
IF NOT SIGNED THIS DOCUMENT IS UNCONTROLLED