Background Image
Table of Contents Table of Contents
Previous Page  40 / 68 Next Page
Information
Show Menu
Previous Page 40 / 68 Next Page
Page Background

38

CONSTRUCTION WORLD

MAY

2015

DAMS AND RESERVOIRS

Besides being used for irrigation

purposes, the dam on White Rocks

Farm is also used for leisure activities.

The dam wall, which had recently undergone

repairs after a previous repair failure, was once

again leaking. The farmer needed an effective,

economical solution that would not entail

costly earthworks or imported materials.

After inspecting the farm dam, Kaytech’s

Paul Lombard suggested that the geosynthetic

clay liner (GCL), EnviroFix, with its simple instal-

lation, would alleviate the problem. EnviroFix,

a proudly South African product manufac-

tured by Kaytech, is produced by needling a

uniform layer of sodium bentonite between

two durable, outer layers of geotextile. Sodium

bentonite is a naturally occurring clay mineral

with a structure comprising charged platelets.

When it comes into any contact with moisture,

it swells considerably, and when this occurs

under confinement, as in EnviroFix, it forms

a lining with such low permeability that it is

equivalent to that of approximately one metre

of compacted clay.

The needle-punching process in the manu-

facture of EnviroFix reinforces the otherwise

weak sodium bentonite, thereby producing

a completely uniform geosynthetic clay liner.

The Thermal Lock process in its manu-

facture is used to modify and permanently

lock the needlepunched fibres into place,

resulting in unique properties such as

increased internal shear resistance and long

term creep resistance.

A local contractor, Grevin Price of Ibhu-

ngezi Technical Services, who has had

SOLUTION FOR LEAKING KZN DAM

On a farm in the scenic Nottingham Road area in the heart of the

KwaZulu-Natal Midlands, Kaytech’s EnviroFix was specified to provide

a cost-effective solution to a leaking farm dam.

>

EnviroFix was laid to

prevent dam leaks.

One year later and the dam is

retaining water as it should.

experience with EnviroFix, by following

Kaytech’s installation guidelines, successfully

installed 4 000 m

2

of non-conformance (NC)

EnviroFix X1000.

The work was successful and was carried

out at a fraction of the cost compared with

that of repairing the wall mechanically.

No specialised equipment was required.

Non-conformance Envirofix is a byproduct

of Kaytech’s stringent manufacturing quality

control programme. It does not meet the strict

specification needed for critical applications

such as composite landfill liners or hazardous

material confinement, however, it is more

cost-effective for a farmer or private individual

to use as it is sold at a discounted price. The

permeability is low enough to use in farm dam/

water confinement applications.

EnviroFix not only provides exceptional

liquid containment, but is also ideally suited

for use in composite landfill liners and caps,

and as a secondary containment barrier in

aboveground impoundments.

The intake tower is accessed from the crest

of the dam embankment by means of a 61 m

long steel bridge.

Pipeline

Delivery of raw water from the dam to the

junction with the North-South Carrier Pipe-

line is via a new 2 MW pumping station, and

a 75 km long welded steel pipeline.

Given that flows and pressure of water

entering the North-South Carrier need to

be continuously synchronised with those

within that existing pipeline, a flow and

pressure control chamber was designed,

which operates in tandem with variable

speed flow pumps in the new pumping

station, controlled from the flow control

chamber via a fibre optic link along the raw

water pipeline.

The Dikgatlhong pipeline is a 1,2

metre diameter welded steel pipe line

and comprises:

• Forty-four scour valve installations

• One hundred and forty six air valve

installations

• Four pigging stations

• One feeder tank for transient pressure

control purposes.

• A flow control chamber

• A meter chamber

• Three river crossings

The pipeline is coated with a three-layer PE

(3LPE) system. While this involves a marginal

increase in coating system cost, the higher

level of mechanical and corrosion protection

provided by the 3LPE system can significantly

reduce the whole-life unit delivery costs.

The Department of Water Affairs demanded

a high level of protection for this critical

pipeline and a technical specification based

on the Canadian CSA Z245.21 pipe coating

standard was used.

The internal lining consists of a two

component solvent free polyamine cured

epoxy coating.

The pipes were welded using gas

shielded Argon root welding by suitably qual-

ified and certified welders. The pipes were

placed in the trenches onto specially manu-

factured pedestals to allow for welding and

coating of the joints.

Sixty-six KV power lines in close proximity

to some sections of the pipeline required

special consideration due to the likelihood of

high corrosion risk due to induced currents in

the pipeline walls.

Specialist surveys were undertaken and

a solution was designed and implemented,

which comprised the application of alter-

nating current mitigation.

Conclusion

The Dikgathlong Dam and Pipeline project

was designed and constructed for Botswa-

na’s Department of Water Affairs to meet

an ever-growing demand for water due to

increased mining and industrial develop-

ment activities – both major contributors to

Botswana’s economy – as well as supplying

potable water to an expanding population in

eastern Botswana.

The project presented the team with

several challenges but construction was

completed on schedule and within the

allowed budget, and the dam water level

has reached full supply level within the last

few months.