Background Image
Table of Contents Table of Contents
Previous Page  42 / 68 Next Page
Information
Show Menu
Previous Page 42 / 68 Next Page
Page Background

40

CONSTRUCTION WORLD

MAY

2015

PROJECT PROFILE

The project entails the replace-

ment of the original NAS using

concrete pipes with a Calcium

Aluminous Cement (CAC) sacrifi-

cial layer, including construction of the asso-

ciated manholes. The total length of the NAS

Phase II is approximately 5,2 km. The three

pipe sizes used for the NAS are 1 650 mm,

1 500 mm and 1 350 mm nominal diameter

respectively. The pipes are 2,44 m in length.

The depth of installation of the NAS

Phase II typically varies between 4 m and

7 m and in terms of bedding preparation,

trenches are dug up to a depth of 8 m. Having

to deal with a water table as high as 500 mm

above ground, adds to the complexity of

the contract.

In addition to the construction of the

new outfall sewer, manholes are constructed

at approximately 90 m intervals, and also at

changes to the vertical and horizontal align-

ment of the sewer, to allow for chambers

(with benching) constructed to terminate

below ground level with access chimneys

constructed to ground level making use of

precast concrete manhole rings.

Construction of the sewer at major road

and railway crossings are carried out by

means of pipe jacking. Two of the pipe jacks

cross some of Metrorail’s main railway lines

and no disruption to commuter services

were allowed while these sections of the

construction were done. Strapping and

extra support structures had to be designed

and installed to prevent any subsidence

of the rail tracks and measures were put in

place to monitor this in conjunction with

the fluctuating water table levels which

had to be maintained. A total of eight

pipe jacks were done during this contract

with the pipe diameter at these sections

varying from 1 470 mm to 1 680 mm and

the length of the jacks varying from

22 m to 84 m. Horizontal directional drilling

technology was also implemented at one

crossing which consisted of a 630 mm diam-

eter HDPE pipe 60 m long.

A section of the existing NAS, a 762 mm

diameter concrete pipe with an approximate

length of 1,2 km will be rehabilitated using

‘cured in place pipe’ (CIPP) technology. This

rehabilitation work comprises cleaning the

sewer, isolating the sewer and over-pumping

the existing wastewater, CCTV inspections

and the installation of the new pipe liner.

Curing of the resins is achieved with the

recycling of heated water.

Construction innovation

technology

CSV Construction has specifically invested

in technologically advanced shoring equip-

ment for this contract which includes

two High Frequency Excavator Mounted

Vibrating Sheetpile Hammers fitted to 30 ton

Hydraulic Excavators and it also imported

a PTC high frequency Excavator Mounted

vibrating pile driver.

The steel sheetpiles that were imported

from Asia are of the Nippon Type FSP IV

Sheetpiles and the ones being used on this

specific project are 7,5 m long. These sheet-

piles are interlocking resulting in a solid

wall capable of deflection and providing a

very effective water cut-off which is much

needed with the ground water level being

generally 1,5 m below NGL but in places as

high as 500 mm above NGL. Sheetpiles are

driven so that the bottom tips (toes) of the

piles are 1,5 m below the trench floor level.

This is to provide adequate toe stability

to the system. Specially designed braces are

used to brace the upper part of the shoring

system, spanning the width of the trench

between the sheetpiles.

CSV also acquired two Japanese manu-

factured Giken Silent Piling machines for

this project. These machines are used to

install Nippon Type FSP IV Sheetpiles, the

same as for the vibrating hammers, but can

also be used for other types of sheet pile

installations. The silent piler makes use of

a press-in method to install piles. The silent

piling technology is applied where the 7 m

deep trenching is carried out as close as

1,5 m from existing sensitive high voltage

cables that could not be exposed to any

vibrations or movement.

Corporate social investment

Although this project mostly involves special-

ised work and is more machine orientated,

10% of CSV’s labour is sourced from the local

ward council’s job-seekers database.

Local businesses and service providers

such as fuel stations, hardware stores,

plant-hire companies, construction supply

companies and other local companies are

well supported due to the close proximity

of industrial areas to the project and we

are also saving on fuel cost by doing local

business. With the employment of about

130 workers on the project the local take

aways and grocery stores also benefit a lot

from this project due to its close proximity

to their business.

A section of the project traverses the

grounds of a technical college with whom

CSV has built up a very good relation-

ship. The company is currently setting up

interviews with civil/building technology

students from this college for employment

as site foremen and supervisors. The aim is

to employ 10 students from this college.

CONSTRUCTION

of the

NORTHERN AREAS SEWER

The Northern Areas Sewer

(NAS) is a major collector

sewer currently serving an

area of approximately

4 100 ha of the northern

suburbs of Cape Town. The

total future catchment area

to be serviced by the

NAS is approximately

4 600 ha of the bigger

Cape Town metropole.

>

Main components of the silent piler.