PROJECT PROFILE

CSV also imported silent-type six-inch,

high volume, high lift water pumps from

the company BBA in Holland, specifically

when it has to work in residential areas with

high volumes of ground water that needs to

be pumped.

Health and safety

On a project of this nature with excavations

up to 8 m deep and the pipes to be installed

weighing in excess of seven tons while huge

machines move up and down throughout the

construction site, health and safety (H&S) is

always a big challenge and therefore remains

a priority. The project route also runs next to

one of Cape Town’s busiest roads which add

to the complexity of traffic accommodation

for the duration of the project.

For this reason a permanent on-site

Safety, Health, Environment and Quality

(SHEQ) Officer has been appointed to keep

H&S up to standard. The SHEQ Officer regu-

larly reports back on health and safety

matters during the project meetings. Every

visitor to the site has to undergo a site induc-

tion session before being allowed to come

onsite accompanied by a senior project staff

member. Being midway through the project,

CSV has only had some minor injuries and no

serious accidents.

Quantifiable time, cost

and quality

The original duration of this project is 78

weeks. With 63% of time lapsed, CSV has

been granted a total of 126 days extension.

which is mainly due to adverse physical

conditions and also due to changes in scope

of work for working in such close proximity

to the sensitive group of 132 kV electrical

cables. Chances are good that more exten-

sion of time will be granted because of many

unknowns and difficult working conditions.

The value of the contract is R139 078 382

(excluding VAT). With all the unknowns, costs

can get out of hand if not properly managed.

For this reason CSV have a permanent Quan-

tity Surveyor (QS) on site to ensure tight

control over the project budget in terms of

costing and forecasting.

CSV has a very strict quality assurance

policy on the project with every step of the

construction process checked and signed

off by both representatives from both the

contractor as well as the consultants. All of

this is well documented and filed accordingly.

Risk management

A full and complete risk assessment was done

before the start of the project and safety

measures were put in place to mitigate these

risks. With the type of ground conditions in

general and the high water table encoun-

tered on site during the winter months

the risk assessment couldn’t stop there.

The risk assessment is an ongoing process

along with the implementation of safety

measures which CSV adjusts as the environ-

ment dictates.

Method statements complete with job

specific risk assessments are prepared

upfront for all major work activities to

ensure safe work practices.

Motivating facts about the

project

Cape Town has not experienced a new sewer

pipe construction project of this magnitude

and especially at this depth in the last few

decades. It is also the first time ever that

a pipe installation of this size, length and

depth of excavation is being done making

use of our method of a ‘forward rolling’ steel

shoring system. The deployment of CSV’s

specialised shoring system has worked well

to date and is demonstrating to clients that

methods less disruptive and costly than the

conventional open cut method are feasible

and available.

The use of the silent piling technique

is not only a first for South Africa, but also

a first for the African continent. The two

silent piling rigs operating in CSV’s fleet are

the only ones of its kind in Africa. The tech-

nology involved in silent piling is ground-

breaking and is providing options, previ-

ously not available to engineers wanting or

having to construct underground services in

close proximity to sensitive infrastructure,

heritage sites and sensitive buildings.

Sheet piles installed with silent pilers.

Installation of 1 650 diameter concrete pipe

while checking line and level.

Project information

• Project start date: 7 May 2013

• Project end date: 15 June 2015

• Client: City of Cape Town

• Project team: City of Cape

Town, AECOM and

CSV Construction

• Main contractor: CSV

Construction

• Project manager: City of

Cape Town

• Consulting engineer: AECOM

• Project value: R139 078 382

(excluding VAT)