Background Image
Table of Contents Table of Contents
Previous Page  43 / 68 Next Page
Information
Show Menu
Previous Page 43 / 68 Next Page
Page Background

41

CONSTRUCTION WORLD

MAY

2015

PROJECT PROFILE

Design innovation

The design of this project is based on a 50 year

design life. Pipes were designed with an addi-

tional special 25 mm thick Calcium aluminate

cements (CAC) layer inside the pipe which

extends the life span of the pipe even more.

CACs are cements consisting predominantly

of hydraulic calcium aluminates which is a

very hard material and can withstand severe

chemical attacks. Pipes are designed to a very

flat grade with 1:600 being the lowest and a

tolerance of 25 mm are allowed for the instal-

lation. The pipes are manufactured by the

horizontal-spun method.

Manholes are in-situ cast concrete

structures and generally 4 m deep and are

located every 90 m or less. Manholes are also

designed with a 2 mm layer of Sika Epocem

720 applied to the inside of the concrete

manhole which extends its life span by a

further 25 to 30 years.

The new pipe services an area of approx-

imately 4 000 ha. Many years of planning and

consultation with various services depart-

ments, local residents and other concerned

parties were done before the designs of the

system could be done/finalised.

Environmental impact

consideration

With excavations generally 6 m deep in

clayish sand conditions and water table

at 1,5 m below NGL (Natural Ground Level)

like CSV is encountering on this project,

the typical open cut method will result in

an excavation width of minimum 20 m wide

or more.

The installation of continuous multi-tier

wellpoints dewatering systems would also

have been required.

The open cut method would have had a

huge impact on the environment giving the

amount of soil to be handled and keeping

in mind the close proximity of residential

homes and other critical infrastructure like

power lines, roads and railways.

WithCSV’smethodof having the two sheet

piled walls driven each side of the trench, the

excavation is confined to an average width

of only 4 m wide. Therefore CSV is handling

less than a third of the amount of soil it would

have with the open cut method resulting in a

much happier environment.

A 450 m section of the new pipe line runs

about 1,5 m away from six 132 kV electrical

cables conveying 15% of Cape Town’s power

supply. These are oil filled cables and are

about 50 years old. Any vibration or move-

ment of heavy machine close by the cables

can cause a failure of the cables. Therefore

CSV proposed the method of sheet pile

installation by means of silent piling. The

proposal was accepted by the engineers and

client and the two machines were imported.

Thus far 300 m of this section is completed

successfully without any damage or negative

impact to the cables or the surrounding resi-

dential buildings.

The silent piling equipment has a

reduced impact on the environmen as it is far

less noisy than the conventional construc-

tion plant.

Installation of sheet piles with excavator

mounted vibratory hammer.

Silent pilers busy with sheet pile installation.