CITY OF MORGAN HILL
CAPITAL IMPROVEMENT PROGRAM
2017-2022 Six-Year Capital Improvement Program
PAGE : 58 OF 123
Project
Charging Stations - CCC/AC/CRC
Project No.
570014
Category
Streets & Roads
Department
Public Works
Council Priorities
Protecting the Environment
Location
CCC/AC/CRC
Project Description
Install three Level 2 plug in electric vehicle (PEV) charging stations for FY 16/17. The PEV charging stations will be
installed at the Community and Cultural Center (CCC), Dennis Kennedy Aquatics Center (AC), and the Centennial
Recreation Center (CRC). Each charging station will be able to charge two vehicles at a time. The electrical
system at each facility will incorporate future expandability, so the costs to add future PEV stations will be
minimal. For FY15/16, the City installed a total of five PEV charging stations at City owned facilities, with the
capacity to charge eight vehicles. For FY 16/17, the City plans to install three more so each City owned facility will
have at least one PEV charging station. For FY 18/19 and FY 20/21, staff will evaluate the need for additional PEV
stations at each City owned facility to determine if more are needed.
The following amounts of the project costs are anticipated from the Transportation Fund for Clean Air (TFCA)
Grant:
FY 16/17: $18,000 for three additional PEV charging stations (2 charging ports per station)
FY 18/19: $30,000 for five additional PEV charging stations (2 charging ports per station)
FY 20/21: $30,000 for five additional PEV charging stations (2 charging ports per station)
The predicted total number of charging stations at City owned facilities at end of FY 20/21 could be as high as 18,
with the capacity to charge 34 vehicles.