CITY OF MORGAN HILL

CAPITAL IMPROVEMENT PROGRAM

2017-2022 Six-Year Capital Improvement Program

PAGE : 62 OF 123

Project

Intersection Capacity Analysis

Project No.

575015

Category

Streets & Roads

Department

Public Works

Council Priorities

Enhancing Public Safety, Planning Our Community,

Developing Our Community

Location

Various Intersections

Project Description

Evaluate major intersections to evaluate traffic efficiency. Report on recommendations for improving the

geometry, lane configuration, and traffic signal timing to move traffic through the targeted intersections in the

most efficient manner.

The focus will be the following intersections: Tennant Ave. & Butterfield Blvd., E. Main Ave. & Monterey Street, E.

Dunne Ave. & Condit Rd.

Project Justification

Improve intersection efficiency based on observed congestion.