CITY OF MORGAN HILL

CAPITAL IMPROVEMENT PROGRAM

2017-2022 Six-Year Capital Improvement Program

PAGE : 59 OF 123

Project Justification

To support the growing use of plug-in electric vehicles within our community. The City will continue to apply for

grant funds to help fund future projects and charge customers a nominal fee in order to recover costs associated

with electricity use and projected maintenance.

Expenditure Schedule & Category

Streets & Roads: 570014

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

86220 - Architecture and Design

$50,000

$15,000

$15,000

86360 - Construction

$180,000

$60,000

$60,000

86530 - Project Implementation

$60,000

$10,000

$10,000

PROJECT COST

$290,000

$85,000

$85,000

Funding Source(s)

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

f347 - Public Facilities Impact Fund

$290,000

$85,000

$85,000

FUNDING TOTALS

$290,000

$85,000

$85,000

Estimated Project Schedule

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

Quarter

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

Planning

__________

Project Design

_____

Right-of-Way Acquisition &

Permitting

Construction

_______

Project Closeout

__

Operating Cost Impacts

The PEV charging stations annual network service plan cost is $255 per port (2 ports per station), for a total of

$1,530 per year. The City adopted a pilot program user fee to recover costs associated with electricity use and

projected maintenance.