CITY OF MORGAN HILL
CAPITAL IMPROVEMENT PROGRAM
2017-2022 Six-Year Capital Improvement Program
PAGE : 63 OF 123
Expenditure Schedule & Category
Streets & Roads: 575015
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
86220 - Architecture and Design
$30,000
PROJECT COST
$30,000
Funding Source(s)
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
f309 - Traffic Impact Fund
$15,000
f346 - Public Facilities (NonAB1600)
Fund
$15,000
FUNDING TOTALS
$30,000
Estimated Project Schedule
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
Quarter
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
Planning
Project Design
__
Right-of-Way Acquisition &
Permitting
Construction
Project Closeout
__
Operating Cost Impacts
There are no operating budget impacts.