CITY OF MORGAN HILL

CAPITAL IMPROVEMENT PROGRAM

2017-2022 Six-Year Capital Improvement Program

PAGE : 69 OF 123

Expenditure Schedule & Category

Wastewater: 303a11

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

86360 - Construction

$1,183,000

$80,000

$80,000

$80,000

$230,000

$13,000

PROJECT COST

$1,183,000

$80,000

$80,000

$80,000

$230,000

$13,000

Funding Source(s)

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

f641 - Sewer Impact Fund

$633,000

f643 - Sewer CIP Fund

$550,000

$80,000

$80,000

$80,000

$230,000

$13,000

FUNDING TOTALS

$1,183,000

$80,000

$80,000

$80,000

$230,000

$13,000

Estimated Project Schedule

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

Quarter

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

Planning

Project Design

__________________________________________________

Right-of-Way Acquisition &

Permitting

Construction

_____________________________________________________________

Project Closeout

Operating Cost Impacts

The ongoing costs of this Capital Project program are expected to decline after peaking in FY 15/16. Much of the

treatment plant's critical infrastructure will have been replaced. These replacement assets will reduce the

likelihood of costly emergency repairs.