CITY OF MORGAN HILL
CAPITAL IMPROVEMENT PROGRAM
2017-2022 Six-Year Capital Improvement Program
PAGE : 72 OF 123
Project
New Trunk Line
Project No.
308a08
Category
Wastewater
Department
Public Works
Council Priorities
Enhancing Public Safety, Maintaining Fiscal
Responsibility
Location
Morgan Hill to SCRWA
Treatment Plant
Project Description
A parallel sewer trunk line is necessary to facilitate the City's planned growth. The project is staged over several
years to span the distance between Morgan Hill and the SCRWA treatment plant. The treatment plant will
complete a planned expansion by 2021. The new trunk line is scheduled to complete the last segment at that
time.
FY 16/17: Design of approximately 21,000 Linear Feet of 30" Sewer Trunk Line from Highland Avenue to Las
Animas Avenue.
FY 17/18: Construction of approximately 21,000 Linear Feet of 30" Sewer Trunk Line from Highland Avenue to Las
Animas Avenue. Design of approximately 16,000 Linear Feet of 30" Sewer Trunk Line from Las Animas Avenue to
Renz Road.
Project Justification
The City's Master Plan anticipates a level of growth within the community. The rate of growth drives the need
for expanded capacity in the sewer trunk line and the capacity of the SCRWA treatment plant. Cost for
expanding capacity of the trunk line will be covered by the collection of sewer impact fees.