CITY OF MORGAN HILL

CAPITAL IMPROVEMENT PROGRAM

2017-2022 Six-Year Capital Improvement Program

PAGE : 67 OF 123

Project Justification

Future development will require that the plant treat a larger volume of wastewater. Preparation for meeting

future wastewater treatment needs requires an on-going flow monitoring and plant expansion design and

engineering program. The Plant Capacity Expansion costs are expected to escalate for the next 4 to 5 years as

the plant expansion is completed.

Expenditure Schedule & Category

Wastewater: 303093

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

86360 - Construction

$693,000

$1,279,000

$4,152,000

$3,053,000

$1,684,000

$421,000

PROJECT COST

$693,000

$1,279,000

$4,152,000

$3,053,000

$1,684,000

$421,000

Funding Source(s)

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

f641 - Sewer Impact Fund

$693,000

$1,279,000

$4,152,000

$3,053,000

$1,684,000

$421,000

FUNDING TOTALS

$693,000

$1,279,000

$4,152,000

$3,053,000

$1,684,000

$421,000

Estimated Project Schedule

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

Quarter

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

Planning

Project Design

_________________________________

Right-of-Way Acquisition &

Permitting

Construction

Project Closeout

________________________________________________________________

Operating Cost Impacts

Increased capacity will meet new user demand. The costs associated with increasing the capacity of the

treatment plant will be paid by new users through the collection of development impact fees.