CITY OF MORGAN HILL

CAPITAL IMPROVEMENT PROGRAM

2017-2022 Six-Year Capital Improvement Program

PAGE : 68 OF 123

Project

Sewer Plant Improvements

Project No.

303a11

Category

Wastewater

Department

Public Works

Council Priorities

Enhancing Public Safety, Maintaining Fiscal

Responsibility

Location

Gilroy Treatment Plant

Project Description

Constructed in 1994, the South County Regional Wastewater Authority (SCRWA) treatment plant requires

ongoing maintenance and improvement while also implementing new standards from the State Water

Resources Control Board. Projects are identified in the FY 2016-2021 SCRWA Capital Improvement Budget and

are funded through wastewater rate payers.

Some of the major projects in FY 16/17 include: Aeration System ($400,000), Secondary Clarifier ($300,000), Pre-

Anoxic Basin ($500,000), SCADA Communication Network ($950,000). The City of Morgan Hill is responsible for

41.9% of the project costs.

Project Justification

Ongoing plant maintenance and repairs are performed to increase efficiency and reliability and necessary to

maintain the plant's operating license.