Edition 47 9-71
Material Handlers
9
Lifting Capacities
●
MH3024
(Grenoble Sourced)
Lift Capacities (continued)
All values are in lb, bucket cylinder and linkage installed, hydraulic cab riser, work tool: none, with counterweight (11,470 lb), heavy lift on.
Load point height
Load over front
Load over rear
Load over side
Load at maximum reach (sticknose/bucket pin)
Undercarriage
Boom
Stick
MH or Standard
22'4" MH
15'9" Straight Stick
Undercarriage configuration
15 ft
20 ft
25 ft
30 ft
35 ft
ft
10 ft
MH – stabilizers up – solid tires
20,100 20,100 14,500 12,900 12,900 9400 9100 9100 6700 6800 6800 4900 5200 5200 3700 4600 4600 3200
37.30
MH – stabilizers down – solid tires
*30,500 *30,500 *30,500 *22,500 *22,500 21,100 *17,800 *17,800 14,600 13,600 13,600 10,900 10,600 10,600 8500 9500 9500 7700
Lower (std UC) – f. stabilizer & r. dozer up
19,900 18,500 13,900 12,600 11,900 9000 8900 8400 6300 6600 6200 4600 5000 4800 3400 4500 4200 3000
Lower (std UC) – f. stabilizer & r. dozer down
*30,500 *30,500 22,500 *22,500 *22,500 14,200 17,400 17,000 10,000 12,900 12,600 7400 10,000 9800 5700 9000 8800 5100
Lower (std UC) – f. dozer & r. stabilizer up
20,600 17,900 13,900 13,100 11,500 9000 9200 8100 6300 6800 6000 4600 5200 4600 3400 4700 4000 3000
Lower (std UC) – f. dozer & r. stabilizer down
*30,500 *30,500 23,200 *22,500 21,500 14,600 *17,800 14,900 10,300 14,400 11,100 7600 11,200 8600 5900 *10,000 7700 5200
Lower (std UC) – 2 sets stabilizersup
20,500 18,400 14,100 13,000 11,800 9100 9100 8400 6400 6800 6200 4700 5200 4700 3500 4600 4200 3000
Lower (std UC) – 2 sets stabilizersdown
*30,500 *30,500 28,400 *22,500 22,100 17,500 *17,800 15,300 12,300 13,200 11,400 9100 10,300 8800 7100 9200 8000 6300
5 ft
MH – stabilizers up – solid tires
18,200 18,200 12,900 12,000 12,000 8600 8600 8600 6200 6500 6500 4600 5100 5100 3500 4500 4500 3100
37.50
MH – stabilizers down – solid tires
*31,300 *31,300 *31,300 *22,800 *22,800 20,000 *17,600 *17,600 14,100 13,300 13,300 10,600 10,400 10,400 8400 *8800 *8800 7500
Lower (std UC) – f. stabilizer & r. dozer up
18,100 16,700 12,300 11,700 11,000 8200 8400 7900 5900 6300 6000 4400 4900 4600 3300 4300 4100 2900
Lower (std UC) – f. stabilizer & r. dozer down
*31,300 *31,300 20,500 *22,800 *22,800 13,300 16,800 16,400 9500 12,600 12,300 7200 9800 9700 5600 8800 8700 5000
Lower (std UC) – f. dozer & r. stabilizer up
18,700 16,100 12,300 12,200 10,600 8200 8700 7600 5900 6600 5700 4400 5100 4400 3300 4500 3900 2900
Lower (std UC) – f. dozer & r. stabilizer down
*31,300 *31,300 21,300 *22,800 20,500 13,700 *17,600 14,300 9800 *14,000 10,800 7400 *10,800 8400 5700 *8800 7600 5100
Lower (std UC) – 2 sets stabilizersup
18,600 16,600 12,400 12,100 11,000 8300 8700 7900 5900 6500 5900 4400 5100 4600 3400 4500 4100 2900
Lower (std UC) – 2 sets stabilizersdown
*31,300 *31,300 26,300 *22,800 21,000 16,600 17,300 14,700 11,700 12,900 11,100 8900 10,100 8700 6900 *8800 7800 6200
0 ft
MH – stabilizers up – solid tires
17,100 17,100 11,800 11,300 11,300 8000 8200 8200 5800 6300 6300 4400 4900 4900 3400
MH – stabilizers down – solid tires
*22,400 *22,400 *22,400 *21,500 *21,500 19,300 *16,600 *16,600 13,700 *12,900 *12,900 10,400 *9400 *9400 8300
Lower (std UC) – f. stabilizer & r. dozer up
16,900 15,600 11,200 11,100 10,400 7600 8000 7500 5500 6100 5700 4100 4800 4500 3200
Lower (std UC) – f. stabilizer & r. dozer down
*22,400 *22,400 19,300 *21,500 *21,500 12,600 16,400 16,000 9100 12,300 12,100 6900 *9400 *9400 5500
Lower (std UC) – f. dozer & r. stabilizer up
17,500 15,000 11,200 11,500 10,000 7600 8300 7200 5500 6300 5500 4100 5000 4300 3200
Lower (std UC) – f. dozer & r. stabilizer down
*22,400 *22,400 20,100 *21,500 19,700 13,000 *16,600 13,900 9400 *12,900 10,500 7100 *9400 8300 5600
Lower (std UC) – 2 sets stabilizersup
17,400 15,500 11,400 11,400 10,300 7700 8300 7500 5600 6300 5700 4200 5000 4500 3300
Lower (std UC) – 2 sets stabilizersdown
*22,400 *22,400 *22,400 *21,500 20,300 15,800 *16,600 14,300 11,300 12,600 10,800 8600 *9400 8600 6800
–5 ft
MH – stabilizers up – solid tires
10,900 10,900 7700 8000 8000 5600
MH – stabilizers down – solid tires
*18,300 *18,300 *18,300 *14,200 *14,200 13,400
Lower (std UC) – f. stabilizer & r. dozer up
10,700 10,000 7200 7800 7300 5300
Lower (std UC) – f. stabilizer & r. dozer down
*18,300 *18,300 12,200 *14,200 *14,200 8800
Lower (std UC) – f. dozer & r. stabilizer up
11,100 9600 7200 8100 7000 5300
Lower (std UC) – f. dozer & r. stabilizer down
*18,300 *18,300 12,600 *14,200 13,600 9100
Lower (std UC) – 2 sets stabilizersup
11,000 10,000 7300 8000 7300 5300
Lower (std UC) – 2 sets stabilizersdown
*18,300 *18,300 15,400 *14,200 14,000 11,100
*Limited by hydraulic rather than tipping load.
Lift capacity ratings are based on ISO 10567:2007, they do not exceed 87% of hydraulic lifting capacity or 75% of tipping load. The load point is the center line of the bucket pivot mounting pin on the stick. The oscillating
axle must be locked. Lifting capacities are based on the machine standing on a firm uniform supporting surface. For lifting capacity including bucket and/or quick coupler, the respective weight has to be subtracted from
above values. The use of a work tool attachment point to handle/lift objects, could affect the machine lift performance.
Always refer to the appropriate Operation and Maintenance Manual for specific product information.