Previous Page  18 / 72 Next Page
Information
Show Menu
Previous Page 18 / 72 Next Page
Page Background

DECEMBER • 2016

Construction

WORLD

16

Civil Engineering Contractors

A

1

MAJUBA RAIL

The 68 km corridor is the first large greenfield freight rail

infrastructure project to be carried out in South Africa since

1986 and will be operated by state-owned logistics provider

Transnet Freight Rail. The project was designed by Transnet

Capital Projects.

Aveng Grinaker-LTA was awarded the contract for construction

activities in January 2013. Construction of the line commenced in

March 2013, with the completion of the civils portion expected in

August 2016.

The objective of the project was to construct an electrified

heavy haul rail link line that ultimately links the Transnet Freight

Rail export coal line with the existing Majuba Power Station rail

yard. The construction of this dedicated railway came about when

Eskom launched an initiative to change the mode of transportation

of coal to a number of power stations, especially Majuba Power

Station, from road trucks to rail transportation, with resultant

positive economic, environmental and social benefits.

The rail line forms part of the Majuba Power Station coal supply

system and is to transport 21 million tons of coal in 100 jumbo

wagon trains per annum.

A major undertaking for the Majuba rail line was the

construction of the U-shaped table drains for surface drainage.

The scope of work required the construction of 63 km of

U-drains in every cut formation, on both sides of the rail line.

Aveng (Africa) Limited used three different methodologies for

this construction, with the third methodology being the most

effective and innovative.

Precast yards were erected at the batch plant sites. Quick

release precast moulds were used to manufacture the precast

units. The precast units were then transported to site where they

were installed where necessary.

The manufacturing of the precast units began in May 2014

and the project produced 30 000 units – enough for approximately

36 000 m – before a decision was made to change the

construction methodology. The teams producing the precast

were notable to produce enough in order to achieve the intended

programme and milestone dates.

Teams continued to manufacture and transport precast units to

site, but also incorporated the construction of in situ U-drains. The

logic behind this methodology was to place a 1,2 m precast unit,

leave a 2,8 m gap and then place another 1,2 m precast unit. The

2,8 m was then cast in situ. A total of 44 000 m was constructed

using methodology 1 and 2.

The third methodology involved slip forming of the remaining

19 km of U-drains, using volumetric concrete batching and a power

curber. A total of 19 000 m in 6 months (3 165 m/month) was

constructed using methodology 3.

Due to rigorous and demanding project milestones, the

teams involved in the construction of the U drains were required

to think out of the box, hence the change in methodology on

numerous occasions.

The methodology involved modern technology by using

a Power Curber slip form machine as well as Reimer self-

batching volumetric trucks. The introduction of fibre reinforced

concrete, although a known concept, had never been used in

conjunction with Reimer volumetric batching and slip form on

such a large scale before and thus a first in the South African

construction industry.

The third methodology involved a substantial amount of pre

planning prior to the methodology being approved by the client

as well as a massive effort from all teams involved during the

execution phase. The site construction teams excelled in many

aspects, such as detailed planning, management of logistics and

value engineered solutions.

The site also achieved 18 months LTI free and in excess of

4 000 000 hours LTI free, resulting in a LTIFR of zero.

The Majuba Rail project is a component of the

Eskom Road-to-Rail Initiative, with the

construction of a railway line that links the

Majuba Power Station to the main coal

railway hub in Ermelo, Mpumalanga.

Winner