Previous Page  21 / 72 Next Page
Information
Show Menu
Previous Page 21 / 72 Next Page
Page Background

2 16

BEST

PR

O

JECTS

19

DECEMBER • 2016

This allowed one track to remain

operational whilst the overhead traction

equipment was transferred from an

existing mast support to the future roof

support position.

During construction the section of

catenary from the ORTIA departure

building to the second OHTE mast had

to be removed. The horizontal tension

force in the catenary after the second

mast therefore had to be resisted.

OR TAMBO GAUTRAIN PLATFORM EXTENSION

Project information

• Company entering: Stefanutti

Stocks Civils

• Client: Bombela Concession

Company

• Start date: 30 May 2015

• End date: 23 May 2016

• Main contractor: Stefanutti

Stocks Civils

• Principal agent: Bombela

Concession Company

• Project manager: Turner and

Townsend

• Quantity surveyor: Stefanutti

Stocks Civils

• Consulting engineer SMEC

South Africa

• Subcontractor: Tass

Engineering

• Subcontractor: ITAL Concrete

• Project value: R80-million

The GRRL was developed as a public private partnership

concession and includes a 15-year maintenance and operation

period after completion of construction. This concession was

awarded to the Bombela Concession Company (BCC).

As part of the maintenance and operation of the Gautrain

system, the BCC recognised the need to extend the station

at ORTIA in order to allow for better commuter access at this

location. The design and construction of the station extension

contract for ORTIA was awarded to Stefanutti Stocks in April 2015.

Stefanutti Stocks employed SMEC South Africa as their design

consultant for the works.

The ORTIA station extension project’s scope of works included

the detailed design and construction of a length of approximately

55 m of extended station platform. The extension now allows

passengers access to four train carriages instead of the previous

two carriage access system.

The principal challenge between the new station installation

and the previous installation is that the current installation has

been constructed and erected whilst the Gautrain remained fully

operational. This resulted in numerous challenges for the erection

and design team.

The main challenge that was encountered was how to safely

lift the 20 t platform slabs a height of 25 m above ground level,

over the 25 kV live train line. Various options were considered by

the contractor, including the use of various mobile and fixed crane

types and even a moving vierendeel gantry frame, which would

have required a rail to be installed in the adjacent road.

The adopted solution was to use a fixed in place heavy lift

crane (the largest in Africa) which met the load and lever arm

requirements for lifting the heavy slabs into place on the southern

side of the viaduct.

In order to mitigate the risk associated with working adjacent

to a live rail line, the design of the station roof had to be revised so

that it could be installed in three sections.

This is because the construction works could only occur over

one track at a time after the OHTE had been switched off and

removed and safety hoarding had been erected between the

two tracks.

The Gautrain Rapid Rail Link (GRRL) is designed

for the rapid movement of commuters between

Johannesburg, Pretoria and the OR Tambo

International Airport (ORTIA) in Gauteng.

One of the goals during the construction period of this station

was to complete the project without impacting or changing the

environment. Changes in the environment in this project entailed,

(a) train traffic schedule, (b) cars and pedestrian working and

travelling around the construction site and (c) car users parking for

long term periods.

This goal was achieved and the construction was completed

without any incident or disruption to the environment. Nightshift

engineering work was restricted to minimum noise.

Pollution of dust was not allowed. During the demolitions,

concrete walls were soaked with water and protective shield

installed to prevent dust pollutions.

This project was executed inside the airport premises, leaving

the contractor with just ACSA and the city lodge hotel as the main

stakeholders involved.

OR Tambo is a key national point for South Africa. With

thousands of passengers from all over the world travelling or

transiting through this airport, the aesthetics and quality of

finished work was exquisite.