Previous Page  26 / 72 Next Page
Information
Show Menu
Previous Page 26 / 72 Next Page
Page Background

DECEMBER • 2016

Construction

WORLD

24

Building Contractors

A

2

The distribution centre was just over 55 000 m

2

under roof in

size, and included 45 000 m

2

of external concrete hardstands.

One hundred and sixty wall panels were cast and erected to form

6 000 m

2

of precast walls.

The wall elements was 10 m high and 5 m wide, and was

installed as a single element, when the lifting started, vast areas of

wall was erected in a day and up to 20 panels a day was achieved,

which equates to about 1 000 m

2

a day.

The ancillary buildings that was constructed consisted of a

main office and change rooms, two sub-stations, a truckers node,

a battery bay, a sprinkler and hydrant pump room, water harvest

tanks, a concrete bridge, a perimeter water channel, a guard house,

and canopies over the docking bays.

Due to the vast size of the project and the tight programme, the

MR PRICE DISTRIBUTION CENTRE

Stefanutti Stocks Building KZN has constructed

a new distribution Centre for Mr Price in

Hammersdale, KwaZulu-Natal. The project

consisted of two phases which was split into

11 months for construction and 12 months for

the mechanical fit out which is not part of the

contractor’s scope of works.

contractor split the distribution centre in half. Constructing it as

two separate jobs to effectively shortened the construction time.

The contractor started the structural concrete works in

both zones at the same time followed by structural steel and so

forth – in essence Stefanutti Stocks were running two projects

concurrently on one site, which allowed them to make progress a

lot faster than if we treated the distribution centre as one.

What was different about this project was that there were three

different sized columns for the entire job, all 10 m high – which

aided the programme.

The columns were cast in one lift, using special techniques

in concrete segregation and vibrating, this enabled us to get the

bolts in very quickly and commenced the next trade which was

structural steel.

The high tolerance floors for flatness were cast after the

building was enclosed to prevent curling and the FM2 specification

in accordance with TR34 was achieved successfully with only

2 m

2

in the whole facility that was 2 mm out of space.

The contractor delivered the project in the 11

th

month, on time,

which had been a mammoth team effort. The project was also

delivered within the required budget.

The contractor employed local labour and upskilled them

significantly, and further developed the skills by enrolling them into

the Master Builders Associations emerging contractor programme

where they developed their business acumen and helped them

moved their business forward in the construction industry.

The building has reverse curves in the roof for natural light,

water harvesting and solar panels.

Project information

• Company entering: Stefanutti Stocks Building KZN

• Client: Mr Price Group

• Start date: July 2015.

• End date: June 2016

• Main contractor: Stefanutti Stocks Building KZN

• Architect: Paton Taylor Architects

• Principal agent: Paton Taylor Architects

• Project manager: Paton Taylor Architects

• Quantity surveyor: Edgecombe & Hayes Hill

• Consulting engineer: Arup

• Subcontractor: Avellini-Impact JV

• Subcontractor: Premier Concrete Floors