Previous Page  32 / 72 Next Page
Information
Show Menu
Previous Page 32 / 72 Next Page
Page Background

DECEMBER • 2016

Construction

WORLD

30

Civil Engineering and Building Contractors (outside South Africa)

A

3

The Senqu River Bridge Project involved the con-

struction of a four span, 140-metre-long composite

steel and concrete bridge over the Senqu River in

the Quthing district of Lesotho, near the town of

Mount Moorosi. Two kilometres of approach roads

linking the Phamong and Quthing districts were

also constructed as part of the project.

SENQU RIVER BRIDGE PROJECT

The Phamong district is situated in a very rural, isolated area in the

southern regions of Lesotho. For many years the only access for

the people of Phamong to the bustling business district of Quthing

was to cross the Senqu River by ferry or on foot.

When the mighty river is in flood, which can be for up to four

or five months of the year, there is little or no access. The building

of this facility was therefore essential to give the people of

Phamong access to vitally needed goods and services from

the Quthing district.

The Senqu River at the project’s location is approximately

150 m wide and has a large sand bed up to 25 m deep in some

places. When the river is in full flood, up to 2 500 m

3

of water

hurtles down between the river banks. For this particular reason,

the design of the bridge dictated a solution which required the

launching of large steel girder truss sections across the river,

followed by the casting of a 250 mm in-situ thick concrete deck

with New Jersey parapets. The four spans of the bridge vary in

length between 30 m and 40 m.

The bridge substructure consists of two abutments situated on

the banks of the river and three piers up to 15 m in height situated

within the river bed. The substructure is founded on 1 100 mm

diameter oscillator piles which vary in depth between 8 m and

22 m which are socketed into the bedrock. The bridge has four

spans varying in length between 30 m and 40 m.

In order to execute the piling and construct the piers, a temporary

rock fill causeway was constructed across the river, which allowed

the dry season river flow to pass through unabated. Access to

the pier foundations for piling and construction equipment was

via this causeway. Due to the large seasonal floods which occur

in the wet season, it was essential that the pier foundations were

constructed during the dry season.

The bridge deck consists of three 2 m deep steel girders laced

together with cross bracing and a 250 mm thick, 12 m wide in-situ

concrete slab cast on top of the beams with in-situ New Jersey

parapets constructed on the sides of the deck.

Twenty metre sections of the three steel girders were pre-

assembled on the launching platform situated behind the eastern

abutment and launched in phases across the river. Launching was

done with the use of two 150 ton jacks mounted to the east bank

abutment with 20 m being jacked out over the river at a time.

The composite steel and concrete deck structure in

combination with the elongated T section piers set against the

back drop of the vast Lesotho mountain range makes for a visually

appealing landscape.

The 2 km of approach roads have a surfaced width of 9 metres

with the layer works generally consisting of a G7 lower and upper

subgrade, a cement stabilized G5 subbase and a G2 crushed stone

base. The Cape seal surfacing consists of a 13,2 mm aggregate

seal and fine slurry.

Local labour working on the project were employed from the

areas around Mount Moorosi and Phamong.

Employees were also educated on life skills, HIV awareness

and environmental awareness. Once the project is complete,

all employees will be issued with a certificate confirming there

involvement in the project and the exposure and training in the

above mentioned areas.

Some 38 000 shifts have been recorded with no lost time

injuries. Given the location of the project and the limited

construction knowledge of the local community working on the

project, this is a remarkable achievement.

Project information

• Company entering: Stefanutti Stocks

• Client: Lesotho Roads Directorate

• Start date: 20 March 2012

• Project end date: 5 October 2015

• Main contractor: Stefanutti Stocks Lesotho

• Consulting engineers: SMEC Consulting

Engineers in association with

Elite Consulting

• Subcontractor: Pennyfarther Engineering

• Cost of project: M150-million

(Lesotho Maloti)

Highly Commended