The second and final phase would encompass the excavation and

lateral support to the new proposed basement layout, including

the demolition and removal of the existing four-basement parking

garage. Challenges were numerous, including but not limited to

unknown location of services, concrete obstructions covered by

soil, a diabase dyke running through the site with the unknown

position and extent, retaining neighbouring property structures and

basements and the most difficult of all, the time constraints.

Due to the nature of the complex goestrata in the location of

the site, the lateral support design had to cater for the constantly

varying soil conditions.

In addition, the neighbouring property structures comprising

the Balalaika, Protea and Holiday Inn Hotels, the Bull Run Pub and

Restaurant, Nedbank Building and the highly traffic-congested

Maude Street and Rivonia Road, all depended upon the absolute

effectiveness of the lateral support design and installation.

The proximity of the neighbouring property basements provided

a further challenge as the required anchor lengths would clash

with the existing basement positions. Accurate surveys had to

be undertaken to determine the location and depth of these and

anchor designs were adjusted accordingly.

Exceptionally long strand anchors were installed along the

Maude Street and Rivonia Road faces while exercising extreme

care not to drill into neighbouring basements.

A grout design capable of complying with strict quality

requirements, but still allowing the tight programme to be met, was

implemented and maintained throughout the project execution.

The lateral support was designed using the observational

129 RIVONIA ROAD

(VILLAGE WALK), SANDTON

In June 2014 the decision was taken by Eris

Property Group to redevelop the old Village Walk

site. The primary phase would support the existing

boundary walls with the Balalaika and Protea

Hotels, this paving the way for the second phase.

method. Numerous unforeseen challenges were encountered

during the lateral support and excavation phase and these had to

be accommodated in the specified programme time. The lateral

support was also complicated by diabase intrusions which was

encountered as water-bearing and often saturated silt and required

additional support.

Blasting of hard rock, constituting a third of the overall

basement excavation volume, was undertaken with precision and

each blast design individually prepared with its own parameters

and restrictions. Overall, in excess of 80 blasts were set off without

a single problem.

The lateral support structure installed had to provide a safe

environment during the earthworks and lateral support contract

as well as for the duration that the building contractor would take

to construct the basement structure. This period would be in the

region of 30 months.

A strict environmental plan was adhered to in order to have

as little impact on the daily activities around the site as possible.

Being a highly traffic congested area, strict traffic control

measures were implemented and maintained throughout the

construction phase. Dust control was continuously enforced with

the use of water bowsers.

The fine balance between time, cost and safety was respected

to ensure that the client benefited from the optimum solution.

Multi disciplines were running in parallel with the lateral support

activities, these including bulk earthworks, blasting, the surgery

precision saw cutting of existing beams and slabs as well as the

bulk demolition of the existing four basement structure.

All disciplines were planned to a micro level to ensure all

contractors could work simultaneously in a crowded and space

restricted environment.

The introduction of the building contractor halfway into the

lateral support contract further complicated the site logistical

challenges. Almost half of the site footprint was handed over to

the building contractor, in early November 2015 with six months

still left to run on the bulk earthworks and lateral support contract.

Working works were strictly adhered to as the three surrounding

hotels with 80% occupancy had an obligation to their guests.

Activities were carried out during working hours and Saturdays

Project information

• Company entering: Franki Africa

• Client: Eris Property Group

• Main contractor: Franki Africa

• Architect: Boogertman + Partners

• Principal agent: SIP

• Project manager: SIP

• Quantity surveyor: Aecom

• Consulting engineer: Aurecon

• Subcontractor: Zero Azani

• Subcontractor: Phoenecian Demotlition

• Contract value: R140 000 000

until 14:00 only, further restricting the overtime

facility to catch up on the lost time.

Therefore, from both a technical and

management aspect, Franki showcased the

optimum solution, bringing the ultimate goal of

a successful project to the client that entrusted

Franki Africa with this responsibility.