Previous Page  39 / 72 Next Page
Information
Show Menu
Previous Page 39 / 72 Next Page
Page Background

2 16

BEST

PR

O

JECTS

37

DECEMBER • 2016

Project information

• Company entering: Kwikspace

Modular Buildings (Kwikspace)

• Client: Gauteng Department

of Education

• Start date: 1 October 2015

• End date: 1 February 2016

• Main contractor: Kwikspace

Modular Buildings

• Principal agent: Gauteng

Deparement of Education

• Quantity surveyor: Kwikspace

• Project value: R25-million

KAALFONTEIN SECONDARY SCHOOL

The scope of works consisted of the construction of 32

classrooms, 10 ablutions, an administration building, a nutrition

centre and additional landscaping works. Faced with a challenging

project deadline and a tight budget, Kwikspace came up with

an innovative solution that enabled them to deliver the new school,

and accommodate 1 468 learners, in just 109 days – less than

1/3

rd

of the time that it would take using conventional brick and

mortar construction.

An irregular site footprint meant that Kwikspace had to

conceptualise an innovative new design to maximise the space

available at the school. It was decided that, along with three single

storey blocks, a double story building would be required to make

efficient use of the space.

To create a sturdy double storey structure it was determined

that concrete floors would be required on the ground and first

floors – a first for modular construction. First a steel structural

frame was assembled, using prefabricated steel components,

and then prefabricated concrete blocks were craned into place

on the frame to form the ground and first floors. The remaining

components were assembled around the frame to form the shell

and façade of the new school building. All the components used,

including the wall panels, windows, doors, roofs and the frame

were prefabricated and transported to Kaalfontein for assembly.

Along with the innovative double story school building,

Kwikspace provided three single storey blocks, one of which was

approximately 94 m long and held 10 classrooms. In another first

for modular construction, the ablutions were incorporated into the

classroom block, in the centre, rather than as a separate building,

which is the standard design of modular schools.

An adminstrative unit was supplied for members of staff which

included a built in strong room, which Kwikspace created using

double thick polyurethane wall panels with reinforced bars.

According to a survey commissioned by the

Gauteng Department of Education (GDE) in 2015,

533 of the 1 856 schools in the province were

overcrowded. To address the urgent requirement

for new classrooms, the GDE awarded Kwikspace

Modular Buildings a R25-million contract to build

a new school for Kaalfontein Secondary School

using alternative building methods.

A nutrition building, with a kitchen and storage area, from which

school pupils receive one nutritious meal a day.

All of these structures were built using traditional, strong

foundations onto which the external façade and roofs were built

using modular components. Despite its rapid delivery, this method

of construction gives rise to a durable structure that requires little

maintenance and has a long lifespan.

The project was split into four phases corresponding to work on

each of the four blocks. Following the completion of each phase,

pupils were immediately taken out of their old mobile classrooms

and shifted into the new buildings. With this in mind the contractor

had to exercise extreme care to minimise dust, noise and make the

area ready after each phase – to ensure a comfortable transition.

The old classrooms were in a terrible state of disrepair and moving

the children into their new premises as soon as possible was

a priority. Despite these challenges, through extensive forward

planning and in close consultation with the school, Kwikspace was

able to deliver a new school for Kaalfontein, in record time, without

disruption to learners.

Creating a design for the school that incorporated all of the new

facilities, on the triangular footprint of land was challenging, but

it inspired us to develop an ingenuitive new double story solution

that we can now roll out on other projects.

Wherever possible, Kwikspace tries to leave a positive

impact on the communities that surround its works. During

construction 95 local community jobs were created and five

local subcontractors were employed to provide paving, plumbing,

electrical, security, landscaping and construction support.

The site team realised that, in order to install the school’s sewer

connection line, they would need to demolish a neighbouring

resident’s existing corrugated iron home, which was sitting directly

on top of the connection. In close consultation with the resident,

the team brought down the existing structure quickly and replaced

it with a structurally superior modular building with strong

traditional foundations.

Special Mention