Previous Page  43 / 72 Next Page
Information
Show Menu
Previous Page 43 / 72 Next Page
Page Background

2 16

BEST

PR

O

JECTS

41

DECEMBER • 2016

GREEN AND FUNCTIONAL HARD

LANDSCAPING FOR SILVERSTAR CASINO

The walls were constructed after an amphitheatre, The Dome,

designed and built by Otto Wijnberger of In2Structures, had been

added to the site.

Backing onto Roodekrans Ridge, the largest wall is 128 m

from end-to-end and tops 6,5 m at its highest point. Running

adjacent to the amphitheatre, it was built by Powergate

Construction at an angle of 70˚. Backfill, which varies in depth

between 3-3,5 m, was reinforced with Kaytech PC 50/50 geofabric

at every third block layer.

Wick drains were installed on the cut face at 45˚ every two

metres and these channel water into a sub-soil drain. Further

drainage is provided by a rain channel which was installed in the

backfill behind the top layer of blocks.

Indigenous trees, grasses and shrubs combine with the

foreground paving to complement and soften the retaining wall

particularly well, while the red soils used for the backfill have

stained the grey blocks, resulting in a colour mix that blends in well

with the surrounding environment.

Three concrete retaining block walls have been built

at the Silverstar Casino entertainment complex in

Krugersdorp using CMA member, Terraforce’s L11

blocks. The blocks were supplied by Terraforce licensee

and CMA member, ReMaCon Products cc, and the walls

were designed by ReMaCon CEO, Silvio Ferarris.

The two other walls, one 95 m long and three metres high and

the other 91 m long and two metres high, were built to secure

embankments on the fringes of two parking areas. Both were built

by Powergate Construction using the same L11 block and to the

same design specifications as the larger wall.

The Terraforce L11 block has a round face finish which is easily

planted. Moreover, the L 11 system is also cost-effective and easily

constructed in uniform concave curves.

Terraforce blocks are exclusively manufactured in Gauteng by

Remacon Products.

MAIZE SILOS AT MASHAMBA,

Democratic Republic of Congo

The findings of the geotechnical investigation conducted by

MSJ were used to determine representative in situ geotechnical

parameters for the geogrid reinforced soil foundation mattress

design. The investigation consisted of 11 TLB dug test pits and

five rotary cored boreholes. Pocket penetrometer tests, vane shear

tests, and point load index tests were carried out in addition to

laboratory testing comprising grading analysis, Atterberg limit

determination, Mod. AASHTO compaction and CBR tests. The

investigation highlighted rock at level between 11 m and 12,7 m

below natural ground level and a completely weathered clayey

zone between 14,2 m and 16 m below NGL. Moreover, rock level

was found between 18,78 m and 20,5 m below NGL. Rock has been

found above these levels but there are also completely weathered

zones and a relatively thick clayey zone between 12,5 m and 20,5 m.

The combination of high pressure loading and the presence of

clay with an undrain shear strength in the range of 50 to 100 kPa

for the first 6 to 10 m resulted in failure in bearing capacity resulting

in the need for foundation improvement techniques. The remote

location of the site has strained and limited the possible solutions

as access and the availability of material and equipment would

have had to be brought in, delaying the execution of the project.

MSJ and Maccaferri Africa had successfully used basal

reinforcement techniques in the past for similar situation and it

has been proven to be cost effective with high margin of safety

and short installation time.

The proposed solution consisted of excavating the in situ

material to a depth of 2 m below the soil mattress level. Two

layers of Paralink

®

600 are then placed bi-directionally (second

layer placed with straps at right angles to the first) onto the in situ

material. A separation layer comprising 100 mm graded gravelly

sand specially selected from the laterite source, lightly rolled, is

placed between the Paralink

®

600 in order to enhance the friction

between the geogrid and the soil in order to transfer the stresses

from the soil.

MSJ Geotechnical Consulting Services were appointed

to carry out the foundation design for the New Maize

Silos at Mashamba, Democratic Republic of Congo in

order to cater for the 322 kPA loading from the strip

footing and 180 kPa from the 28 m high maize.

Project information

• Company entering: Remacon

• Start date: May 2015

• End date: October 2014

• Main contractor: WBHO

• Consulting engineer: Remacon Products

• Subcontractor: Powergate Construction

Project information

• Company entering: Maccaferri Africa

• Start date: January 2016

• End date: March 2017

• Project team: MSJ Geotechnical

Consulting Services

• Consulting engineers: MSJ Geotechnical

Consulting Services