Previous Page  41 / 72 Next Page
Information
Show Menu
Previous Page 41 / 72 Next Page
Page Background

2 16

BEST

PR

O

JECTS

39

DECEMBER • 2016

AUAS HILLS RETIREMENT VILLAGE

Project information

• Company entering: Namwall

• Specialist supplier: Terraforce

• Client: Stefanutti Stocks

• Project start date: 15 May 2014

• Project end date: 1 March 2015

• Main contractor: Stefanutti Stocks

• Project value: NAD2 400 000 000

In addition to the walls inside the property, a river running

alongside the retirement village needed erosion control retaining

walls, in case of heavy water run-off during the rainy season.

Steffanuti Stocks, the main contractor on site, approached

Namwall, a Windhoek-based, Namibian licensee for Terraforce, to

provide a design for Terraforce block-retaining walls.

“We consulted with Terrasafe, Terraforce’s professional design

service, and had a design ready in no time,” says Namwall’s Chris

Schutte. “Most of the proposed rock-face block walls were pretty

straightforward, with the higher ones requiring a double skin

of L12 blocks for extra reinforcement. In total about 25 000 blocks

were installed.”

The project was completed with Andre’s Landscaping adding

the final touches to the walls.

During the planning stages of the upmarket Auas Hills

Retirement Village, situated in Auasblick, Windhoek,

it became evident that earth-retaining measures

were necessary in order to stabilise the exposed

embankments as a result from excavation activities.

BOSJES CHAPEL

Project information

• Company entering: PERI

• Client: Longworth & Faul

The intricate chapel roof is 20 m long x 12 m wide and 6 m high at

the top apex. It was agreed that a 1:50 quarter concrete demo ‘cup’

is constructed at the Cape Town demo area. The client, architect,

engineer and the whole Bosjes project team were involved and

also present when the gunite was done. A lot of detail and input

was given with regards to the rebar/steel, spacers and practical

application placing the concrete.

It was proven that Gunite was inadequate and the scope

changed to shotcrete. This proved again that concrete demo

samples be done from the start, which is extremely important

when doing these very intricate formwork project.

The formwork erection and concrete placing was programmed

for 12 weeks but took much longer due to the spesialised

carpentry involved , and the inclement Cape Town winter weather.

PERI Cape Town's Edmund Jenneke and Theo Conradie were

involved from the start with the set-out points. PERI formwork

proposal and actual solution was to break this structure down to

see it as simple as possible. It workshopped this and decided to

‘build a ship' and ribs/trusses.

Theo Conradie used Autodesk inventor and designed 584

trusses. PERI procured rooftrusses from a reputable supplier and

manufacturer. Trusses were delivered to the Cape Town branch as

per construction programme priority sequence. All trusses were

properly marked and checked for alignment before delivery to site.

Concrete finish required

• Smooth, and would be skimmed skimmed afterwards.

The architect met with Frikkie Swanepoel two years

ago to dicuss the formwork involved. Based on

previous sucsessfull projects of this intricate nature,

the architect went ahead with designing his concept.

Sequence of formwork erection

• Shoring towers c/w platforms was erected set-out points and

levels plumbed and checked.

• Trusses placed in position from below and from the top

• 38 mm timber battens was fixed horizontally as temporary and

false formwork

• Shutterply was fixed in layers, 12 mm + 4 mm final layer

PERI's design capabilities was put to the test and Theo Conradie

excelled at designing all the trusses and the full project. There was

no crane on site and all formwork, including the timber trusses,

were placed by hand.

The construction sequence was not easy. The full project

team was involved. PERI initiated the PERI template of involving all

parties involved and it created the Architectural Concrete

Team template.