Previous Page  45 / 72 Next Page
Information
Show Menu
Previous Page 45 / 72 Next Page
Page Background

2 16

BEST

PR

O

JECTS

43

DECEMBER • 2016

The Stefanutti Stocks Axsys Joint Venture (SSA JV) was

awarded the contract for the rehabilitation of berths 1-4, 13 and

14 in April 2014, a total of 6 out of 15 berths at Maydon Wharf,

the Port of Durban’s largest break bulk, edible oils and dry bulk

handling precinct.

Maydon Wharf was developed for the then expansion of the

Durban harbour, in particular to meet the needs of the growing

Witwatersrand. The berths were built of timber, with berths 1-4 and

13 and 14 later rebuilt using steel sheet piles in the 1950s.

As the largest and busiest shipping terminal in Southern Africa,

the aged berthing structures require far greater capacity than the

original 20 000 DWT vessels it was originally designed for to meet

current and future demands.

The reconstruction of Maydon Wharf consists of demolishing

the existing quay structure, the removal of old timber piles,

installing a new steel combination wall with concrete cope beam

and back of quay layer works. Included in the scope of works is the

deepening of the seabed by some 4 m to achieve a draft of

14,5 m CD, with the placement of scour rock adjacent to the quay

wall, preventing washout by the propellers of the vessels.

The design of a water tight shutter system for the cope beam

construction was complex and required rigorous analysis. Initially,

a detailed concept of a coffer dam was developed. The coffer dam

concept was however discarded due to handling issues that will

be caused by the overall weight of the structure (approximately 30

tons) and the large windage

area provided by the plating.

The effects of wind in the

marine environment require

thorough consideration in

ensuring the safety of our

teams and for safe handling

of loads.

Another innovative

feat was the construction

of cope beam. A sound

solution came in the design

of a hanging shutter.

Project information

• Company entering: Stefanutti Stocks

Marine

• Name of client: Transnet

• Start date: April 2014

• End date: February 2017

• Main contractor: Stefanutti Stocks

Axsys Joint Venture

• Principal agent: Transnet Group

Capital

• Consulting engineer: RCE Consultants

• Project value: R760 817 570

(excluding VAT)

REDDFORD HOUSE SCHOOL

Project information

• Company entering: LCP

Roofing

• Client: Reddord House

• Start date: June 2015

• End date: December 2015

• Main contractor: Murray &

Dickson

• Architect: Centrury Property

Development

• Quantity surveyor: Bain &

Heyns Quantity Surveyors

and Project Managers

• Consulting engineer: C-Plan

• Contract value: R46 024 231

The newly constructed Reddford House School in Northcliff,

Randburg, was capped by an impressive 8 820 m

2

of timber roof

trusses of varying styles and configurations by local leader in

roof truss technology, LCP Roofing. The exposed timber roof truss

work at the school is remarkable. The architectural design and

layout of both these main buildings allow for optimal functioning

and maximum usage of the space, and upon arrival, the sheer size

and aesthetics of the structures make an immediate and profound

impact on the viewer.

LCP Roofing was tasked with fabricating and erecting exposed

timber feature trusses at the gatehouse, main building entrances,

piazzas and the main hall. The client brief called for a number

of exposed timber roof trusses in as many viable spaces in the

buildings as possible, and even the walkways were to be exposed

and supported by laminated pine beams at the eaves. While

structural soundness was paramount, the aesthetic value of the

project was a prominent consideration for the client.

The architect, Michael Bishop of Century Property

Developments, provided detailed sketches of the client’s

requirements, to which the LCP Roofing team answered with

precision, ingenuity and attention to detail. LCP Roofing’s design

office turned the concept sketches into workable blueprints

that allowed the aesthetic components of the project to push

boundaries, all while maintaining the highest level of structural

integrity, collectively making for an outstanding end result.

The trusses in the main hall proved to be challenging, not only

from a design perspective, but from a logistical point of view. With

a pitch of 27 degrees over such a span, a one-piece truss with

a continuous top and bottom chord would simply be too big to

deliver. The solution was to fabricate the trusses in three sections

instead of one, using two two-ply half

modified scissor trusses and a separate

one-ply top hat truss.

Once completed, the modified design

was sent to LCP Roofing’s supporting

engineers for final specification on the

specific fixing, which was ultimately the

use of a sliding shoe on the wall plate

on one side of the building as well as the

necessary bracing details.

Once fabricated and delivered, the

scissor trusses had to be assembled on

site and the top hat trusses were erected

As South Africa’s principal container port generating more

than 60% of revenue, the Maydon Wharf infrastructure upgrade

will result in much needed increased capacity for the country’s

economic functioning and growth, and will alleviate the congestion

currently experienced.

The SSA JV team is proud to have been part of delivering a key

development project for the client and ultimately, the contribution

to society, it will make in employment opportunities in Durban.

Great care is taken to ensure zero harm to the little marine life

that exists in the port through efforts in using biodegrad-

able grease on sheet pile clutches, and biodegradable shutter

oil and foam seals for the shutters.

RECONSTRUCTION AND

DEEPENING OF MAYDON

WHARF: Berths 1-4, 13 & 14

in the Port of Durban

only once the exposed scissor trusses were in place. A mobile

crane was required to hoist the 19,5 metre span trusses above the

double volume of the hall and then to lower them, one by one, into

position. The crane was only available for a limited period of time,

so the LCP Roofing team worked as efficiently as possible, using

the apron of scaffolding along the side of the walls of the hall

provided by the principal contractor.