Previous Page  40 / 72 Next Page
Information
Show Menu
Previous Page 40 / 72 Next Page
Page Background

DECEMBER • 2016

Construction

WORLD

38

Specialist Contractors or Suppliers

B

The scope of works included structural and spalling repairs,

waterproofing and painting of the entire facade of the building.

Spalling repairs involved removal of all concrete and ribs

until sound concrete was reached, when a coating of Sika

FerroGard-903+ was applied. Designed for use as a surface-applied

impregnation of steel reinforced concrete, Sika Ferrogard-903+

is a mixed corrosion inhibitor, based on organic compounds that

penetrate the concrete to form a protective monomolecular layer

on both cathodic and anodic zones of the reinforcing steel.

This exceptional product with its advanced formulation that

delays the onset of chloride-induced corrosion in hardened

concrete, meets numerous international standards.

Due to the CBD location of the building and the fact that

there were people working inside the building during the

renovations, the smallest breaker was used in order to minimise

impact and vibrations, as well as keep noise levels as low as

possible. After hours applications were carried out using larger

breakers when necessary.

Potential pollution to the city was prevented by installing

platforms with catch netting which served to catch rubble, product,

or any other debris that might fall off the building, due to the work

27 WALE STREET

Project information

• Company entering: Sika

• Client: Cape Town Department of

Transport and Public Works

• Main Contractor: Indawo

Sika’s globally acclaimed Concrete Repair and

Protection Systems was the first choice for consultants

Naylor Naylor and van Schalkwyk for 27 Wale Street,

a prominent government building in the city centre

of Cape Town. Commissioned by the Department of

Transport and Public Works, construction company

Indawo began the challenging project in March 2015.

being carried out, and then disposed of in the correct manner.

Health and safety officers from Ingozi Management Safety

and Health Consultants were on site daily to ensure proper safety

measures were met. External construction work on any building in

a central business district (CBD) poses significant environmental

and safety issues and when the building is in the centre of Cape

Town, one of the world’s top tourist destinations, these issues are

exacerbated. The safety of all pedestrians, motorists, tenants as

well as construction staff was of paramount importance.

ALICE LANE PHASE III

Having already successfully completed the rst two phases of the

Alice Lane Precinct, WBHO was appointed as the main contractor

for the next phase of this prestigious project. Intelligent and

strategic planning allowed WBHO to select a system that would

alleviate the crane time required for construction of critical path

elements on the project.

PERI Formwork Scaffolding Engineering South Africa was

awarded the contract for the supply of formwork, and used the

RCS hydraulic self-climbing platforms on the lift core structures.

The lift core structures posed some special challenges, which

included: changing door opening levels and locations, varying pour

heights and changes in shaft geometry, which varied from closed

boxed sections, to open U-section scenic lift arrangements.

To accommodate these challenges, PERI’s design and projects

teams engineered the following processes:

• Customisation and strategic positioning of the RCS system, to

successfully accommodate the scenic lifts.

Alice Lane Phase III is the third phase of the exciting

Alice Lane Precinct, which consists of three distinctive

buildings linked by a public piazza. The site is located

in the busy heart of Sandton and ideally suited for the

inaugural use of PERI’s RCS hydraulic self-climbing

system – a rst for South Africa.

• Positioning of the RCS rails and climbing shoes in the walls with

the door openings. Because of the varying heights of the slab

levels, anchor hole locations were pre-drilled to ensure perfect

positioning in the header beams.

• Structural changes also in uenced the VARIO wall formwork

design, as internal shutters had to be designed to accommodate

the ground oor shaft openings, due development into scenic

lift geometry.

• The exibility of the RCS platforms ensured that planned in-situ

modi cations were easily completed once they emerged from the

closed shaft formation at ground level.

Project information

• Company entering: PERI

• Main contractor: WBHO