Previous Page  42 / 72 Next Page
Information
Show Menu
Previous Page 42 / 72 Next Page
Page Background

DECEMBER • 2016

Construction

WORLD

40

Franki was awarded the contract in October 2015. They

commenced with the detailed design and mobilised to site

in December 2015 to commence site operations in early

January 2016. The foundations project was completed on

time in July 2016.

Franki used the Dynamic Compaction technique to compact the

in-situ materials to a design depth of 10 m below ground working

level. The compaction was carried out in three different phases

known as the primary, secondary and ironing phases, in this order.

Compaction of the deepest layer is achieved with the primary

phase. The secondary phase achieves compaction mainly in the

intermediate layers. The ironing phase ensures overlapping of the

initial phases by compacting the shallow layers between

the initial prints.

Franki employed the services of GETEC, a Keller company,

which specialises in vibration and movement/settlement

monitoring and recording.

A system was installed on existing tanks which allowed for

remote monitoring and reporting. Targets and a total survey station

were fixed to the existing tanks with remote references and a

predetermined reading timetable was set and readings were taken

automatically and transmitted to GETEC in the UK for analysis and

reporting. This together with a 3 m deep isolation trench allowed

operations to proceed without incident or stress, to the existing

nearby storage tanks.

Safety was as always paramount and Franki and their

subcontractor Civils 2000 were awarded the BCT Best Company

Safety Awareness trophy for 2016.

Specialist Contractors or Suppliers

B

DORMAC QUAY WALL

The new facility consists of the state of the art composite floating

dock supplied by Ukraine-based Pallada builders and a new 185 m

long, 16,9 m high (4 m above and 12 m under water) purpose built

quay constructed by Franki Africa.

The scope of work consisted of the construction of the main

quay structure, the closing in of the existing slipway, installation

of two large diameter mooring dolphins and the excavation and

dredging of the fill and in-situ harbour silts in front of the quay

wall. The engineering design of all civil and geotechnical work was

carried out by Franki Africa’s in-house technical team with support

from Young and Satharia Consulting Structural and Civil Engineers.

The main quay structure was designed for a total retained

As part of Dormac’s R300-million investment in the

Durban Harbour, Dormac Marine and Engineering’s new

floating dock facility, ‘Dormac Dock 1’ would go a long

way towards meeting the demand for ship repair in

South Africa’s busiest harbour.

height of 16 m under

various wave conditions

and berthing directions and

scenarios. The quay wall

consisted of 26 m long,

900 mm diameter

continuous flight auger

(CFA) piles with gaps

between piles sealed with

jet grout columns. The

soldier pile quay wall was

laterally restrained using

steel tie-backs anchored to

anchor piles behind the wall.

Project information

• Company entering: Franki Africa

• Client: Dormac

• Start date: December 2015

• End date: September 2016

• Main contractor: Franki Africa

• Consulting engineer: Young & Satharia

• Subcontractor: Subtech

• Subcontractor: Leomat

• Project value: R65 948 000

BURGAN CAPE TERMINALS FUEL STORAGE

Project information

• Company entering: Franki Africa

• Client: Burgan Cape Terminals

• Start date: December 2015

• End date: July 2016

• Main contractor: Chemi-Tech

• Subcontractor: Civils 2000

• Project value: R23 100 000

In 2015 BCT signed a 20 year lease agreement with the Port of

Cape Town for the use of the site on the Eastern Mole. The site is

a reclaimed area made up of demolition rubble of concrete and

the like in a variable soils matrix overlying weak soil horizons to

depths of 20 m and more. This presented an engineering challenge

to achieve acceptable settlement limits for the proposed large

storage tanks.

Burgan Cape Terminals (BCT) is an independent

storage company constituted by VTTI B.V.

(Holland). JICARO (RSA) and Thebe Investment

Corporation (RSA) to develop a much needed fuel

storage facility in the Port of Cape Town.

The innovative combination of CFA piling and jet grouting allowed

the lead time and construction programme to be reduced to

meet the fast-tracked deadlines. The soldier (CFA) piled wall

was finished with a continuous capping beam which provided

a connection between the soldier piles and the steel tie-back

anchors. Precast panels were positioned on the seaward side of

the capping beam, which acted both as a wall preventing water

ingress as well as the formwork for concreting.

The dock will allow an additional 45 dockings per year.

An extensive environmental impact assessment was carried out

prior to the civil works beginning and strict controls with continual

monitoring were required throughout construction. As this project

is the first in Durban Harbour to involve the removal of land (rather

than the reclamation thereof), the majority of the excavated

material was uncontaminated harbour silts and could be dumped

at specified marine dump sites or at land fill sites.

Both Franki and Dormac pride themselves on exceeding health

and safety standards and having amongst the best records in their

respective industries. All employees on this project underwent

job specific safety training and were subject to regular in-house

and external audits ensuring compliance. This contributed to the

overall success of the project and resulted in the works being

completed with 120 000 injury free man-hours.