Previous Page  28 / 72 Next Page
Information
Show Menu
Previous Page 28 / 72 Next Page
Page Background

DECEMBER • 2016

Construction

WORLD

26

Building Contractors

A

2

Project information

• Company entering: GVK-Siya Zama Construction

• Client: Port Elizabth Opera House

• Start date: 24 March 2014

• End date: 20 November 2015

• Main contractor: GVK-Siya Zama Construction

• Architect: The Matrix

• Principal agent: The Matrix

• Quantity surveyor: Markus Burri QS

• Consulting engineer: AfriCoast

Consulting Engineers

• Project value: R24 113 559

As the only surviving example of a Victorian Theatre in Africa,

leading specialists in the construction, renovation and recycling of

buildings, GVK-Siya Zama was enlisted to ensure that it would be

preserved for future generations to enjoy.

The topography presented the contactor with tight spaces and

tricky heights: approximately 10 m x 10 m, on a 12 m slope of more

than 45 degrees. Getting big machines into that space for the

excavations was a challenge and the stability of the embankment

was always a concern. The contractor excavated from the top

down first and continuously made sure that the embankment’s

angle of repose was within reliable limits to ensure that there

was no slope failure.

Options were explored to deal with these challenges. External

consultants were called in to conduct thorough geotechnical

explorations. Borehole extractions measured not only the water

table levels but also the condition of the rock.

The contractor decided to dig an additional 1,75 m – more

than double foundation depth – and to then build back up again

with imported layer works, using soil raft foundation, so that

the floor levels of the new and existing building could meet. The

foundations were also reinforced to allow for any possible further

settlement. Once construction of the new, extended facilities were

finished, the project moved inside.

• New staircases and lifts were constructed within the shell of the

existing building

• The original staircases had to be cut out and the existing roofs

supported while that support structure was gone

As the Opera House is a heritage site, strict regulations were

applied to the design and construction work, and the architect

received official sign-off before work began.

That said, especially on such an old building, once the contractor

starts opening up, there are all kinds of surprises and the team

discovered that the drawings simply did not match what they

found inside. Despite having designs to start with, many aspects

had to be redesigned based on site conditions – and as everyone

was working in a tight time frame, there were times when pressure

started running high.

As there was insufficient leg-room for theatregoers in the

suspended Gallery, it was decided to increase the size of each step

but reduce the number of rows. There were no existing plans of the

structure, so new plans had to be drawn up.

The size of this upstairs theatre area needed to be increased

– however, the rock face is so close to the building that there

was simply no room for traditional extension supports. Instead,

innovative and modern-looking suspended clip-on boxes were

designed to provide additional room. The heavy steel support

columns, though, were found to be in the way of the new fire

escape, so they had to be shifted around until they were no longer

an obstruction. Now in place, they offer a chunky, industrial

aesthetic appeal that is in pleasing contrast to the ornate Victorian

character of the original building.

It is difficult to get a heritage building to within the Green Star

rating requirements, because the origin of material and methods

of construction are not clear. However, we are always cognisant of

environmental best practice and strived to incorporate the Green

Star guidelines in terms of our applications. On the Opera House,

the contractor used material such a concrete cement containing

extenders like fly ash, to reduce the carbon footprint.

Approximately 30% of the work was allocated to local emerging

contractors, particularly start-up construction labour contractors.

PORT ELIZABETH

OPERA HOUSE

The oldest theatre on the African continent and

in the southern hemisphere, the PE Opera House,

has recently undergone intricate renovations and

expansions. The building was transformed from a

heritage site into a first class facility.