GAZETTE
judge had been correct to conclude that
Curust had established a triable issue that the
1986 agreement was valid under Article 85
of the Treaty of Rome; (2) although Curust
had acted in breach of contract by recom-
mencing manufacture of the primer without
Loewe's consent, this did not disentitle them
to interlocutory relief since something in the
nature of turpitude would have to be in-
volved to disentitle them to equitable relief;
(3) although the evidence indicated that there
would be a difficulty in ascertaining any
damages which might be payable to Curust
in the event of their succeeding, this would
not be impossible, and having regard to the
fact that the damages would be a quantifiable
commercial loss and that Loewe would be
able to meet any such sum, the plaintiffs had
not established that damages would not be
an adequate remedy, and so had not made
out a case for an interlocutory injunction. Per
curiam: a factor in the refusal of interlocutory
relief was an estimate that the substantive
action could be heard in the High Court in
Spring 1993 and the parties should expedite
the pleadings on this basis.
Gannon v B & I Steampacket Co Ltd,
Landliner Travel Ltd and Edenderry Trans-
port Ltd High Court, 3 July 1992; Supreme
Court, 5 November 1992
JURISDICTION OF COURTS - WHETHER PARTY PROP-
ERLY JOINED - BOAT AND COACH TRIP FROM IRE-
LAND TO ENGLAND - TRIP BOOKED WITH IRISH
SHIPPING COMPANY - COACH PROVIDED BY ENG-
LISH COMPANY - TRAFFIC ACCIDENT INVOLVING
COACH AND LORRY - WHETHER SHIPPING COM-
PANY MAY BE SUED FOR BREACH OF IMPLED TERM
OF CONTRACT - WHETHER ENGLISH COMPANIES
MAY BE JOINED - ABUSE OF PROCESS OF COURTS -
Jurisdiction of Courts and Enforcement of Judgments
(European Communities) Act 1988 - Rules of the Supe-
rior Courts 1986, 0.26, r.2
The plaintiff booked a boat and coach trip
from Ireland to England through the first
defendant, B & I, an Irish company. The
coach was provided by the second defend-
ant, Landliner, an English company. During
the journey, the coach was in collision in
England with a lorry owned by the third
defendant, Edenderry. The plaintiff sustained
personal injuries and instituted proceedings
against the defendants. As against B & I, the
plaintiff claimed that it was in breach of
contract in connection with the choice, op-
eration and driving of the coach involved in
the case. The claim against Landliner and
Edenderry was in tort, and the plaintiff joined
them as defendants in reliance on the 1968
Brussels Convention, enacted into Irish law
by the 1988 Act. Landliner and Edenderry
applied under 0.26, r.2 of the 1986 Rules to
have service of notice of the proceedings set
aside. In the High Court HELD by Denham J
refusing to set aside service: there was a
reasonable case for the plaintiff to sue B & I
in contract, and although the other defend-
ants were being sued in tort there was a
connection between all defendants and so
Landliner and Edenderry were properly
joined. On appeal HELD by the Supreme
Court (Finlay CJ, O'Flaherty and Egan JJ)
allowing the appeal and setting aside the
service of notice: (1) although there were
grounds for the plaintiff to sue B & I, the Court
was required under the 1968 Convention to
inquire further whether a party was joined in
proceedings for the purpose of ousting the
jurisdiction of the courts of the State of other
parties being joined; and since, from the
evidence adduced, it appeared that the col-
lision between the coach and the lorry was
not due to any defect in the coach or the
competence of the driver of the coach and
therefore any claim against B & I would be
" very difficult to sustain, the Court was driven
to the conclusion that the reason for suing B
& I appeared to be to oust the jurisdiction of
the English courts, and on that basis the court
should refuse to allow the plaintiff to join
Landliner and Edenderry, under Article 6 of
the Convention.
KalfelisvBankhausSchroder
(Case 189/87) [1988] ECR 5583 applied; (2)
si nee the removal of Landl i ner and Edenderry
from the proceedings would involve a preju-
dice to B & I, as B & I would be unable to join
them as third parties, an application by B &
I to have the plaintiff's proceedingsdismissed
for being an abuse of the processes of the
courts would be successful.
Cork County Council v Whillock Supreme
Court 3 November 1992
MALICIOUS INJURIES - TIME LIMIT - WHETHER EX-
TENSION PERMISSIBLE - STATUTORY INTERPRETA-
TION - Malicious Injuries Act 1981, ss.14, 23
The respondent claimed that a fire which
occurred at his premises on 13 November
1983 was caused maliciously. On 14 No-
vember 1982, he served on the applicant
Council a preliminary notice of intention to
apply for compensation for malicious inju-
ries under the 1981 Act. S.23 of the 1981 Act
sets out a three year limitation period from
the date on which the cause of action ac-
crues, which is the date of the service of the
preliminary notice. No proceedings were
instituted by the end of the limitation period,
but the respondent applied to the Circuit
Court for an order extending the time for
making a claim under the 1981 Act. This was
granted by the Circuit Court judge on the
ground that s.14 of the 1981 Act permitted
such extension. The applicant applied on
judicial review for an order quashing the
Circuit Court decision. In the High Court,
Carroll J granted the order sought. On appeal
HELD by the Supreme Court (O'Flaherty,
Egan and Blayney JJ) allowing the appeal:
there was no inconsistency between s.23 of
the 1981 Act, which provided for a three year
time limit, and s.14 of the 1981 Act, which
perm itted the C i rcu it Cou rt to extend the ti me
for any act or proceedings under the Act
itself; and having regard to the obligation on
a court to give effect to the literal meaning of
the words of legislation and that it should
avoid an interpretation which would render
a provision inoperative, the Circuit Court
judge had the jurisdiction to make the order
in the instant case.
Dublin Corporation v
Carroll
[1987] IR 410 overruled.
Connolly v Dundalk UDC and Mahon &
McPhillips Ltd Supreme Court 18 Novem-
ber 1992
TORT - EMPLOYER'S LIABILITY - MAINTENANCE OF
EQUIPMENT BY INDEPENDENT CONTRACTOR -
CONTRIBUTORY NEGLIGENCE - DEGREE OF FAULT -
Civil Liability Act 1961, s.21(2)
The plaintiff and one other person were
employed by the UDC to operate its water-
works. As part of the water purification proc-
ess, chlorine gas mixed with water was
4
APRIL
1993
pumped from a chlorine room through a rigid
plastic pipe into a control building to an
upstand pipe into which the mixture was
discharged. A length of flexible plastic pipe
joined the rigid pipe and the upstand pipe in
the control room. The control building and
chlorine purification plant had been built by
Mahon & McPhillips in 1968; in 1972, they
entered into a contract to service and main-
tain the system three times a year; and in
1981, they had replaced the pipe between
the chlorine room and the control building.
In January 1986, on the arrival of the plaintiff
in the control building, he was hit with a
dense cloud of chlorine gas, some of which
he inhaled. He suffered some physical inju-
ries as a result but was also severely affected
mentally by the incident. In the High Court
([1990] 2 IR 1), O'Hanlon J held that the
accident was caused by a failure of the joint
between the rigid and flexible pipes, result-
ing in the release of the chlorine gas. He held
that both defendants had been negligent and
he apportioned liability equally between
them. Damages of 280,727 were awarded.
On appeal by the UDC on the issue of
apportionment only HELD by the Supreme
Court (Finlay CJ, O'Flaherty and Blayney JJ)
allowing the appeal: (1) although the UDC
were negligent in failing to notice that the
joint in question was unsuitable and in failing
to acquaint themselves in time with the de-
velopment of safety procedures which had
come to be regarded as standard, they were
also entitled to rely on the greater expertise of
Mahon & McPhillips in connection with the
construction and maintenance of waterworks;
and having designed and erected the water-
works, and contracted for the periodical serv-
ice and maintenance of the equipment,
Mahon & McPhillips owed an obligation to
the UDC to keep it informed of changes in
standards, and although a recommendation
had been made in this regard in August 1985
(which had not been acted on by January
1986), the trial judge had found that Mahon
& McPhillips should have reacted sooner in
this regard; (2) the trial judge's equal division
of liability between the parties failed to have
sufficient regard to the greater degree of
contribution by Mahon & McPhillips to the
injuries sustained by the plaintiff, within the
meaning of s.21(2) of the 1961 Act; and
bearing in mind Mahon & McPhillips' greater
expertise, very much less blame attached to
the UDC's engineers for failing to discover
the inadequacy of the joint in question; and
accordingly the Court would apportion 80%
liability to Mahon & McPhillips and 20% to
the UDC.
Per
O'Flaherty (Finlay CJ concur-
ring): an employer remains primarily liable in
law for, and cannot fully delegate to an
indepenedent contractor liability for, the
employer's duty to provide a reasonably safe
place of work for its employees; but where an
independent contractor is solely responsible
for causing injury, the employer is entitled to
claim a contribution from the contractor
which would amount to an indemnity.