March 2017
•
MechChem Africa
¦
25
⎪
Petrochemical industries, oil and gas
⎪
T
he existing 865 km Mozambique to
Secunda Pipeline (MSP) for natural gas
from Mozambique to South Africa is
currently the only sustainable source of
natural gas to South Africa and, in order to meet
the demand for natural gas in South Africa, the
transportcapacityofthislinehasbeensignificantly
increased. In order to facilitate this increase, a
combination of compressors and parallel lines – at
approximately128kmper section–had tobebuilt.
The Republic of Mozambique Pipeline
Investment Company (ROMPCO), owner of the
existing pipeline, represents a joint initiative
between Sasol, Companhia Mocambiçana de
Gasodutoand theSouthAfricanGasDevelopment
Company (iGas), and has played a pivotal role in
commercialisingMozambique’s natural gas supply.
With the backing of a successful first project,
Loop Line 1, Sasol Group Technology, which was
spearheading this project at ROMPCO’s behest,
appointed VGI Consulting Africa as the EPCM
contractor for the Loop Line 2 (LL2) undertaking.
The 26-inch LL2 adds further capacity to the
system through the installation of a 127 kmparal-
lel pipeline to the existing MSP line that ties back
into the MSP. The importance of this gas supply
cannot be understated. Much of the supply is fed
to the Gauteng region in South Africa, a commer-
cial and industrial hub that has earned the city of
Johannesburg the title of ‘Africa’s powerhouse’.
This feeder line supports residential, commer-
cial, power generation and industrial heating
requirements in the Gauteng area. Further to
this, the supply also supports the operations of
Sasol’s liquids and chemical plants in Secunda and
Sasolburg as well as other large, energy-intense
industries nearby.
Commissioning of LL2 with Energas
mobile heater skids
For the commissioning of LL2, the new line was
filled and pressurised from atmospheric pressure
to a line pack pressure of 116 bar. The filling gas
had tobepreheated toensure the temperaturedid
not dropbelowthepipelineminimumdesignmetal
temperature of zero – due to the Joule Thompson
cooling effect –while the flow ratewas controlled
andmonitored. A flow totaliser added the benefit
of measuring the normalised volume of gas con-
sumed to achieve the required line pack.
The project specification called for the design,
manufacturing and supply of a transportable skid-
mounted electrical gas heater with flow control
in accordance with ASME 31.8, ASME VIII and
SANS 10108. Design, fabrication, complete as-
sembly and testing of the heater skidwere done in
SouthAfricabeforedeliverytositeinMozambique.
Laetitia Botha, Energas Technologies product
engineer comments: “Energas specialises in the
Energas Technologies has completed a commission to design and supply a mobile heater
skid for the high-pressure natural gas line between Mozambique and South Africa.
The heater skid comprises a thyristor control panel, a
416 kW heater with isolation valves, flow meter, filter,
instrumentation and manually operated control valve
to measure, heat and control the filling of LL2 during
commissioning.
Mobile heater skid
for 127 km natural gas pipeline
design, manufacture and supply of skid-mounted
pressure reduction and metering stations to the
natural gas industry. Most of these skids are for
sites in remote areas and being able to complete
the fabrication and assembly in South Africa sig-
nificantly reduces schedule risk, siteestablishment
and workforce logistics.
“Another benefit of the mobile heater skid is
that it could be relocated and used at different
site points or locations as the new pipeline sec-
tions were being constructed. The heater skid is
only required once during the commissioning of
a new section and it is therefore not required as a
permanent installation. It’s a cost-effective solu-
tion to invest in amobile skid that canbe relocated
where needed.”
The heater skid comprises a thyristor control
panel, a 416 kWheater with isolation valves, flow
meter, filter, instrumentation and manually oper-
atedcontrol valve tomeasure, heat andcontrol the
filling of LL2 during commissioning. The thyristor
controller monitors the gas temperature at the
outlet of the control valve and controls the power
to the heater’s elements in order to maintain an
outlet gas temperature of 10 °C. During commis-
sioning the electrical heater was powered by a
diesel generator.
AMokveld equal percentage axial flowmanual
control valvewas chosen to control theflowof gas
from 116 bar to, initially, atmospheric pressure.
This required a special trim that allowed precise
control while noise and vibrations were very low.
The control valve andheating capacity allowed the
LL2 commissioning team to make effective use of
the gas volumes made available by the pipeline
operator, leading to the pipeline being commis-
sioned much sooner than originally anticipated.
“The natural gas industry both in South Africa
and Africa is a growing one and has a bright
future ahead. We have directly felt the effects
of this growth through ongoing skid manufac-
turing projects in Ghana, the Western Cape and
Mozambique,” Botha concludes.
q