28
¦
MechChem Africa
•
March 2017
A
ccording to Alastair Gerrard, man-
aging director of Zest Energy, the
new generator being constructed
inSouthAfrica for thenewgraphite
mine in Balama will begin producing electric-
ity during the first quarter of 2017, with an
initial capacity of 12.5 MW from an instal-
lation of seven 2 200 kWdiesel generators.
“The isolated location of the Balamamine
– over 250 km west of Pemba in northern
Mozambique – means that while the opera-
tion does have access to power from the na-
tional grid this will need to be supplemented
to ensure an adequate supply for full plant
demand,” Gerrard says. “We are therefore
required by the customer to ensure 100%
availability, and have consequently designed
the plant with substantial standby capacity
to allow formaintenance and repairswithout
affecting the continuous supply.”
The remote operation to mine one of the world’s largest finds of
high grade graphite – the Balama deposit in Mozambique – will
be powered by a generator plant being constructed through
South Africa-based Zest Energy, part of the Zest WEG Group.
Mobile power for Kamoa-Kakula mine
development in the DRC
One of the diesel generator sets for Syrah Resources’ Balama graphite project,
custom engineered and constructed by Zest Energy.
The Zest Energy mobile substation in position on site, connected to the SNEL electrical network. The
photograph shows preparations for hot commissioning and energising in progress.
Balama Graphite Mine
powered by SA-built
He says the plant,
which was the larg-
est footprint project
yet tackled by Zest
Energy, would ini-
tially run with seven
2 200 kW genera-
tors; six running and
one on standby, and
would later be ex-
panded to include
eleven generators,
of which two will be standby units.
Equipment for the extensive scope of sup-
ply has been sourced fromvarious companies
within the Zest WEG Group, locally and
worldwide. The containerised power genera-
tors includeWEGalternatorswith automatic
voltage regulation systems, as well as mo-
torised louvres, generator auxiliary systems,
and fuel and lube tanks. To cool the engines,
a horizontal-type radiator system, rated for
50 °C ambient temperature, was manufac-
tured in South Africa and each radiator in-
cludes 10WEG3.0kWfanmotors positioned
in two cooling banks of five fans each.
“Oneofthechallengesofthemineenviron-
ment is the presence of graphite dust, which
Thedevelopment of theworld’s largest high-
grade copper deposit – the Kamoa-Kakula
Copper Project in the Democratic Republic
of Congo (DRC) – is now running on power
from the DRC’s national grid using a mobile
substation recently commissioned by South
Africa’s Gauteng-based Zest Energy.
The 120/11 kV mobile substation will
serve the construction of the planned initial
mine at Kamoa-Kakula, a project whose
existing mineral resource has been inde-
pendently verified as Africa’s largest copper
find. Kamoa-Kakula’s principal owners are
IvanhoeMines, ZijinMining and the govern-
ment of the DRC.
“Due to the high cost of running on diesel
generators, the mine developers decided to
purchase a mobile substation to interface
with the network of the DRC power utility,
SNEL, toprovidepower during the construc-
tion phase of the project,” Alastair Gerrard,
managing director at Zest Energy, says.
Although the substation will not be
moved frequently, Gerrardsaysbeingmobile
allowed for quick and hassle-free construc-
tion and commissioning, and gives the mine
the addedflexibility of deploying the substa-
tion to other areas of its operations when
needed in the future.
ZestEnergy–partoftheZestWEGGroup
–undertook thedesign,manufacture, supply,
testing, delivery, installation and commis-
sioning of the complete mobile substation,
including the trailer, transformer and related
electrical equipment. It also provided a pro-