Simon Storage - Tyne Terminal
Tank 24 Road Loading Upgrade - Installation Scope of Work
P & I Design Ltd
DOCUMENT NO: SI204001_INS
2 Reed Street, Thornaby, UK, TS17 7AF
ISSUE: A DATE: 20.06.14
Tel: + 44 (0)1642 617444
PAGE 5 OF 5
Fax: + 44 (0)1642 616447
www.pidesign.co.uk3.6
Scope of Work – Local Pneumatic Panel
The panel is to be re-piped to accommodate the two stage pneumatic control to the
batching valve shown on drawing SI347012_DWG.
The works comprise, briefly :-
Remove the manual open switch, blanking panel door suitably
Remove the I/P converter.
Install a second Solenoid valve and regulator.
Install a new shuttle valve.
Re-pipe as shown on drawing SI347012_DWG.
Connect cable SOV12A/CP3 to the new Solenoid Valve
3.7
Scope of Work – Batching Valve
The existing batching valve is to be replaced with an identical unit.
The works comprise, briefly :-
Remove tubing from existing valve
The existing valve will be removed from the pipeline and replaced by others.
Replace tubing to new valve
3.8
Free Issue Equipment
The following will be free issued to the installation contractor, all other equipment to
complete the installation shall be provided by the installation contractor.
Turbine meter
Batcher
I.S. isolator XY004
Batching valve complete with actuator and positioner
Pneumatic components for control panel comprising :-
o
1 off 24Vdc solenoid valve (Note : existing 24Vdc solenoid valve to be
recovered and re-used)
o
2 off regulators with gauges
o
1 off shuttle valve