Background Image
Previous Page  33 / 60 Next Page
Information
Show Menu
Previous Page 33 / 60 Next Page
Page Background

DIAMONDS

March 2015

MODERN MINING

31

A

lthough Liqhobong has been

mined in the past, the new proj-

ect will see mining at the site on

a much larger scale. The new

US$185,4 mine is designed to

deliver 1,1 million carats a year over 15 years,

which is roughly 10 times what nearby Letšeng

– Lesotho’s best known mine – produces (al-

though the dollar price per carat of Letšeng’s

stones is the highest of any kimberlite mine in

the world).

The project is based on mining the main pipe

(there is also a satellite pipe) at the site down

to 393 m over 15 years, exploiting a reserve of

over 11 million carats at a grade of 32,07 cpht.

The anticipated average strip ratio of waste

to ore is 2,28. The ore will be treated in the

Main Treatment Plant (MTP) which utilises a

conventional flowsheet comprising scrubbing,

screening, crushing, concentration via DMS,

and final recovery using X-ray machines. The

plant will have 2 x 250 t/h streams.

According to Firestone Diamonds, the first

six months of the construction phase – which

started in late June 2014 – encountered both

winter and summer weather conditions. The

winter was relatively mild which enabled the

project to start well and the project team to get

ahead on a number of work streams before enter-

ing the start of the rainy season in November.

The above average rainfall experienced in

November and December and delays expe-

rienced in the issuing of work permits to the

civils and earthworks contractor had an initial

negative impact, necessitating a re-scheduling

of certain works and increased work load. The

project team also encountered areas where

excess top soil needed to be removed which, in

combination with the wet weather, caused days

to be lost through personnel not being able to

work safely. Additional crews were deployed to

ensure that development remains on schedule

and within budget.

Work on the residue tailings facility starter

wall and the accommodation terraces is also

progressing well. Overall, as at the end of

Liqhobong

off to a

strong start

View of the site in January

this year (photo: Firestone

Diamonds).

Firestone Diamonds, the AIM-quoted diamond development company

developing the Liqhobong mine in Lesotho, says that the project is currently

within budget and on schedule to achieve initial production at the end of H1

2016. In its recently released results for the six months ended 31 December 2014,

the company says achievements thus far include a safety record of zero lost time

injuries and the creation of approximately 1 000 jobs in Lesotho.

December, the project was marginally ahead of

schedule with significant progress being made

on the construction of the tailings dam wall, as

well as other earthworks and site preparations.

Design, engineering and procurement were set

as a priority by the development team and sig-

nificant progress has been made ahead of the

scheduled targets to ensure the smooth comple-

tion of the project.

The provision of electrical infrastructure

to connect the mine to grid power is a sepa-

rate undertaking which is also progressing

as planned. The total grid power project cost

is R165 million with Firestone funding R145

million and the balance of R20 million being

funded by the local company engaged to con-

struct the power infrastructure. All equipment

and long lead item orders have been placed

and site preparation for the substations is

well advanced. Connection to grid power is

expected to be achieved during the second half

of 2015, ahead of the initial schedule.

At the end of December, a total of R1,28 bil-

lion in orders out of the total budgeted R1,43

billion EPCM contract (being undertaken by

DRA) had been placed. The three largest sub-

contracts under the EPCM contract, totalling

R943 million, have been agreed on a fixed

price/cost basis to remove price escalation risk.

The grid power and Main Treatment Plant

projects combined have created over 1 000

local jobs, and it is expected that the level of

employment will continue to increase as con-

struction progresses.

Connection to

grid power is

expected to be

achieved during

the second half

of 2015, ahead

of the initial

schedule.