Clinical Research Building RFP

7. Compensation

Please provide the following:

Building Shell

Lump sum pre-construction phase fee including reimbursables.

J. Raymond – Our Preconstruction Services typically run between

$5,000 and $7,000 per month. With the goal of developing a long term

relationship between J. Raymond Construction Corp and Onix Group, J.

Raymond will provide Preconstruction Services at no charge to the

Owner. Pre-Approved, pre-defined reimbursable costs shall be direct

pass through charges invoiced directly to the Owner for payment.

Examples of reimbursable items include: Airfare, car rental and hotel

for trips to home office, document reproduction and shipping, etc.

Cost per month for extended pre-construction services beyond

scheduled completion of these services

J. Raymond – We anticipate preconstruction services to run from mid-

January 2017 (start of Design Documents) and run through May 1,

2017 (Permit submittal). Should preconstruction services be required

through Permitting, J. Raymond will contribute at no cost to the Owner

except for reimbursable as defined above.

Percentage fee for construction phase services

J. Raymond – J. Raymond proposes a 3.25% fee on all construction

phase costs

Construction staffing matrix to include hours and costs.

J. Raymond – See attached General Conditions Estimate

General Conditions breakdown in detail based on your schedule.

J. Raymond – See attached General Conditions Estimate