Previous Page  25 / 56 Next Page
Information
Show Menu
Previous Page 25 / 56 Next Page
Page Background

September 2016

MODERN MINING

23

COAL

Cementation’s involvement at Impumelelo –

which is an entirely ‘greenfield’ project – has

extended well beyond the underground bunker.

“We were appointed in 2011 as the contractor

for the sinking of the two vertical shafts – the

main and ventilation shafts – the mine requires

and also for decline development,” he says.

“The first resources arrived on site in May 2011,

although the formal sod turning and contract

signing only took place several months later

in August. Both vertical shafts have been sunk

to a depth of 200 m with the main shaft being

11,7 m in diameter and the vent shaft 6,5 m.

The decline is 1 000 m long, dips at 17 deg and

has a width of 6,5 m and a height of 3,5 m.

“We commissioned the main shaft in

December 2014 and in January 2015 the first

Continuous Miner (CM) – eventually there will

be 10 CMs – started cutting coal. In August

2015 we commissioned the decline conveyor

to 4 Seam and in the following month the ven-

tilation shaft fans were commissioned. With

the coal bunker having become operational

on 9 June 2016, we are now all but complete

at Impumelelo with the final value of Murray

& Robert’s contract – including the bunker –

being R1,06 billion.”

Turning to the coal bunker, Wells says it was

constructed over a period of a year (starting in

May 2015), with Murray & Roberts Cementation

commissions on schedule

Above:

Isometric view of the

box front structure.

Left:

Coal discharging into

the 1 500-ton capacity bunker.

Note the steel walkway – this

alone weighed 3,5 tons.

Centre:

The box front showing

the feed level (below) and

chute level.

Below:

Chute level of the box

front. Each chute weighs about

4 tons fully assembled.

deploying a team of just under 100 to undertake

the work. Excavation extended over roughly the

first six months with construction – civils and

structural steelwork – occupying the remain-

ing six months. “It was a massive undertaking

and we were under huge pressure to meet mile-

stones but fortunately we were able to meet all

the critical interface dates,” he comments. “I

attribute the success we had to the intensive

planning we put into every phase of the opera-

tion and also the cooperation and support we