Previous Page  27 / 56 Next Page
Information
Show Menu
Previous Page 27 / 56 Next Page
Page Background

September 2016

MODERN MINING

25

COAL

The main shaft headgear at

Impumelelo.

steel was fabricated by Louwill Engineering),

are the girder beams, with a total mass of

50 tons, and the supporting columns and floor

steel, with a total mass of 40 tons (excluding

the floor decking and handrails). Says Wells:

“The eight main girder beams have dimensions

of 11 m in length and 1,5 m in height. They

were taken underground in sections which

then had to be spliced together, with each

splice requiring 92 bolts. In fact, we had one

employee totally dedicated to looking after the

bolts and ensuring that none went missing!

Similarly, the sixteen 10 m long columns sup-

porting the feeder and chute levels also had to

be spliced together.

“We planned everything to the last detail,

with the steel being laid out on the bank at

surface and hard stamped and marked to allow

us to get everything to the workplace in the

right sequence with the right bolts and splic-

ing plates. Everything was placed on sleds on

surface to facilitate handling and taken down

in the cage of the main shaft. Once under-

ground, these sleds were towed by an LHD to

the workplace.”

Certain elements of the structure – for exam-

ple, the floor grating and the vibrating feeder

frame (which is independent of the rest of the

structure) – were trial assembled on surface,

again to reduce the chances of any unforeseen

problems arising during installation.

Highlighting some of the more interest-

ing parts of the overall bunker project, Wells

notes that the logistics of concrete supply were

challenging. “Concrete pours which on sur-

face would be routine become difficult when

undertaken 200 m or more below surface,” he

explains “We had to transfer the concrete – a

pumpable mix supplied by Lafarge – from sur-

face to 4 Seam level via large diameter drilled

and cased aggregate holes and then distribute it

using a positive displacement concrete pump.

Alongside each aggregate hole, we needed

a communication hole so that teams on sur-

face and underground could liaise. The key

was to avoid blockages in the aggregate holes

– unblocking them could be very time consum-

ing – and we were generally very successful in

achieving this objective.”

Although not within the scope of the origi-

nal contract, the electrical and instrumentation

(E&I) work for the bunker and box front –

including the installation of a MCC panel – was

undertaken by Murray & Roberts Cementation.

“We both procured and installed the E&I sys-

tem,” says Wells. “This is not normally part of

our service offering but we were asked to take

it on and the work went very well.’

Finally, Wells notes that the Impumelelo

project was recently named as the best per-

forming project within the Sasol Mining group,

receiving the ‘Best Overall Performance of the

Year’ Award for 2015 from Kobus Louw, Sasol

Mining’s Vice President, Projects & Sigma.

“The award recognises the achievements of

the entire team responsible for designing and

implementing Impumelelo including Sasol

Mining itself, as well as the EPCM contractor

– the RSV ENCO Hatch Goba Joint Venture –

and the major contractors, notably Murray &

Roberts Cementation and – in the case of mate-

rials handling – ELB Engineering Services,”

says Wells. “The bunker, of course, represents

only part of the overall project but is neverthe-

less a critical part of the mine’s infrastructure

and we’re proud of the fact that we’ve been able

to deliver it on time and within schedule – and,

perhaps most importantly of all, with an excel-

lent safety record.”

Photos by Arthur Tassell