![Show Menu](styles/mobile-menu.png)
![Page Background](./../common/page-substrates/page0027.jpg)
September 2016
MODERN MINING
25
COAL
The main shaft headgear at
Impumelelo.
steel was fabricated by Louwill Engineering),
are the girder beams, with a total mass of
50 tons, and the supporting columns and floor
steel, with a total mass of 40 tons (excluding
the floor decking and handrails). Says Wells:
“The eight main girder beams have dimensions
of 11 m in length and 1,5 m in height. They
were taken underground in sections which
then had to be spliced together, with each
splice requiring 92 bolts. In fact, we had one
employee totally dedicated to looking after the
bolts and ensuring that none went missing!
Similarly, the sixteen 10 m long columns sup-
porting the feeder and chute levels also had to
be spliced together.
“We planned everything to the last detail,
with the steel being laid out on the bank at
surface and hard stamped and marked to allow
us to get everything to the workplace in the
right sequence with the right bolts and splic-
ing plates. Everything was placed on sleds on
surface to facilitate handling and taken down
in the cage of the main shaft. Once under-
ground, these sleds were towed by an LHD to
the workplace.”
Certain elements of the structure – for exam-
ple, the floor grating and the vibrating feeder
frame (which is independent of the rest of the
structure) – were trial assembled on surface,
again to reduce the chances of any unforeseen
problems arising during installation.
Highlighting some of the more interest-
ing parts of the overall bunker project, Wells
notes that the logistics of concrete supply were
challenging. “Concrete pours which on sur-
face would be routine become difficult when
undertaken 200 m or more below surface,” he
explains “We had to transfer the concrete – a
pumpable mix supplied by Lafarge – from sur-
face to 4 Seam level via large diameter drilled
and cased aggregate holes and then distribute it
using a positive displacement concrete pump.
Alongside each aggregate hole, we needed
a communication hole so that teams on sur-
face and underground could liaise. The key
was to avoid blockages in the aggregate holes
– unblocking them could be very time consum-
ing – and we were generally very successful in
achieving this objective.”
Although not within the scope of the origi-
nal contract, the electrical and instrumentation
(E&I) work for the bunker and box front –
including the installation of a MCC panel – was
undertaken by Murray & Roberts Cementation.
“We both procured and installed the E&I sys-
tem,” says Wells. “This is not normally part of
our service offering but we were asked to take
it on and the work went very well.’
Finally, Wells notes that the Impumelelo
project was recently named as the best per-
forming project within the Sasol Mining group,
receiving the ‘Best Overall Performance of the
Year’ Award for 2015 from Kobus Louw, Sasol
Mining’s Vice President, Projects & Sigma.
“The award recognises the achievements of
the entire team responsible for designing and
implementing Impumelelo including Sasol
Mining itself, as well as the EPCM contractor
– the RSV ENCO Hatch Goba Joint Venture –
and the major contractors, notably Murray &
Roberts Cementation and – in the case of mate-
rials handling – ELB Engineering Services,”
says Wells. “The bunker, of course, represents
only part of the overall project but is neverthe-
less a critical part of the mine’s infrastructure
and we’re proud of the fact that we’ve been able
to deliver it on time and within schedule – and,
perhaps most importantly of all, with an excel-
lent safety record.”
Photos by Arthur Tassell