Previous Page  26 / 56 Next Page
Information
Show Menu
Previous Page 26 / 56 Next Page
Page Background

24

MODERN MINING

September 2016

COAL

The decline conveyor seen from the box front. It has a belt width of 4,6 m/s and is rated at

2 900 tph. The extension of the conveyor under the box front was undertaken over four days

in May this year.

Above:

Simplified cross

section through the bunker

and box front.

had at every step of the way from our client,

Sasol Mining.”

The bunker feeds ore to the decline con-

veyor which has a capacity of 2 900 tph and

a belt speed of 4,6 m/s. With this capacity,

the conveyor system can empty the bunker –

assuming no inflows – within 27 minutes.

Describing the bunker, Wells says it has a

finished diameter of 14,7 m and extends 24 m

down from the 4 Seam horizon (200 m below

surface) to the soffit floor of the box front

chamber. The bunker has a cylindrical section

of 16,5 m and – below that – a conical section

of 5,5 m. The box front chamber extends a fur-

ther 10 m to the footwall of the decline on the

2 Seam horizon.

According to Wells, the first task was to

create a collar ring beam at 4 Seam level to

facilitate excavation of the bunker. “To do an

excavation of this type, you need a decent infra-

structure,” he says. “So we excavated a top cut

to a depth of 1,8 m using an LHD and an exca-

vator. The ring beam itself has dimensions of

1 m x 1 m and – including approach slabs –

required 200 m

3

of concrete to be poured. To

excavate the barrel of the bunker, we opted to

use drop raising to sink a 4 m diameter cen-

tre core which was then slyped out to the full

diameter of 14,7 m. We supported the side-

walls as we advanced using mesh, shotcrete

and rock anchors. In all, the bunker excavation

amounted to 5 800 cubes.

“To establish the profile of the conical sec-

tion – which we only did earlier this year once

the box front was completed – we used sand-

bags to form a back shutter and then backfilled

behind these bags with mass concrete. In all,

we used 6 800 sandbags during this phase of

construction.”

He adds that the volume of shotcreting was

huge with 450 cubes of mass fill shotcrete being

required for backfilling with an additional

126 cubes of 70 MPa andesite shotcrete, 300 mm

thick, being placed on two layers of mesh as

the final step in the operation. “This andes-

ite shotcrete was very unforgiving in terms of

pumpability and flowability,” notes Wells.

While the excavation of the bunker was

by no means an easy task, the construction of

the box front – which houses the chutes and

vibrating feeders controlling the discharge of

coal to the decline conveyor system – proved

equally demanding. “Put simply, this is primar-

ily a steel structure but with massive amounts

of concreting required for the floor slab, the

16,5 m long, 10 m high and 1 m thick east and

west side walls and the 1,5 m thick soffit or

roof,” he notes. “Altogether we poured over

1 800 m

3

of concrete. Given the dimensions of

the side walls, we elected to make use of wide

scaffolding. These walls, incidentally, each

required 30 tons of reinforcing.”

The main elements of the steel structure (the