CITY OF RALEIGH
PUBLIC UTILITIES
Monthly Performance Report
FY 15 (July 2014-June 2015)
22
All financial data is from the city’s financial management system. This is an unaudited report.
Project Name
Project
Manager
Current
Phase
Vendor
%
Completion
Date
Status
FLOCC & Sed. Basin
Full Scale Pilot
ES
Design
Hazen & Sawyer 95%
11/2014
Continuing Design
Raw Water Reservoir Cover
PA
On Hold
-
0%
-
On Hold
Sodium Permanganate
Improvements
PA
Design
Hazen & Sawyer 95%
12/2014
DWSRF Application for
0% Loan Approved
Clearwell Rehabilitation
RR
PER
Brown and
Caldwell
17%
-
Clearwell Assessment Diving
Complete
Wastewater Collection and
Pumping Improvements
(Phase II)
PA
On Hold
Jacobs
-
-
Reassigning Contract
Warehouse Expansion
PA
Design
Municipal
Engineering
100%
9/2014
Bid Date August 2014
Raw Water Reservoir
Sludge Removal
PA
On Hold
-
-
-
-
UV/Solids Handling
PA
-
-
-
-
-
EMJ WTP PROJECTS
Project Name
Project
Manager
Current
Phase
Vendor
%
Completion
Date
Status
Settling Tank
Dewatering Facilities
DL
PER
Jacobs
95%
9/2014
Advertise RFP/RFQ
August 2014
Wrenn Road Lagoon
Improvements
DL
Construction
Water & Waste
Construction
95%
9/2014
Demonstration/Substantial
Completion
Backwash Waste
Recycling Facility
PA/RR
Construction
Wharton-Smith,
Inc.
50%
12/2014
-
DEB Reservoir
EN
Design
Hazen and
Sawyer
-
-
Received SUP February 2014
DE BENTON PROJECTS