Sanitary Sewer Siphon Rehabilitation
RR
Design
Hydrostructures 95%
9/2014
Reviewing 95%
Plans
Marsh Creek Sanitary Sewer Replacement
RR
Construction
Centurion
Construction
95%
9/2014
90% of Main
Interceptor and
100% of Laterals
Chamberlain, Clark SS Replacement
ES
Construction
Moffat Pipe
70%
3/2015
Added Section of
Sewer Replacement
on Hold until July
Hammond Rd SS Relocation
RR
Scoping
Dewberry
-
TBD
Project Information
Meeting in August
Gorman St. Sewer Rehab./Replacement
AB
Construction
Moffat Pipe
35%
12/2014
Working on Tunnel
at Burgess
Aerial Crossing Replacements II
RR
PER
URS
75%
-
Desktop Review
Extended
Aerial Crossing Replacements I
RR
Design
Dewberry
90%
-
Submitted to
Development
Review
Leafcrest Sewer Realignment
AB
Construction
Moffat Pipe
0%
12/2014
N-T-P
February 2014
Lake Wheeler Rd Stream Relocation
RR
Design
Kimley-Horn 60%
1/2015
City Coordination
Meeting in August
Beaman Lake Creek Interceptor Evaluation
JG
Study
Hydrostructures 50%
-
Flow Monitors
Removed, Report
Underway
Upper Pigeon House Sewer Interceptor
Replacement
EN
Design
GHD
100%
2/2016
Advertisement in
August
Ashe Av/Park Av/Cox Av Water and Sewer
Replacement
DL
Construction
JF Wilkerson
Contracting
0%
4/2015
N-T-P July 2014
Eton Rd Sewer and Aerial Replacement
DL
Design
Aecom
100%
4/2014
Negotiations and
Settlement
Seaboard Station Sanitary Sewer Evaluation
AB
Planning
Edens Land
Corp.
0%
12/2014
Scoping
Lower Marsh Creek Interceptor Evaluation
RR
PER
Hydrostructures 100%
6/2014
Complete
North Hills Dr, East St, E. Lenoir, Corporation
Pkwy CCTV Investigation
DL
Design
Hydrostructures 50%
11/2014
Design in Process